H-<strong>SAF</strong> Project Plan 2.0, October 2007 - Update PP-2.2, 10 April 2008 - Chapter 2 (From the Development Proposal) Page 36<br />
The official documents for the ORR (User Manual and Final Report) will include:<br />
• User Manual:<br />
- essential product descriptions (reasons for the product, sensing principle)<br />
- main sensor features controlling product geometry and accuracy<br />
- information for data access and handling (dissemination means, format, coding, schedule)<br />
- information on data quality (resolution, observing cycle, timeliness, accuracy / error structure)<br />
- description of user services (archive, web site, help desk);<br />
• Final Report:<br />
- description of the final system architecture and configuration<br />
- summary description of products basis, algorithm and development phases<br />
- summary report of products validation activities and results<br />
- summary report of hydrological validation results and benefit assessment.<br />
Bakground documents for the ORR will be:<br />
• the latest version of ATDD (presumably, ATDD-2.0 or some minor update);<br />
• the final issue of the rolling internal document REP-3 (H-<strong>SAF</strong> Products Validation Report);<br />
• the final issue of the rolling internal document REP-4 (H-<strong>SAF</strong> Hydrological Validation Report).<br />
A synoptic view of the evolution of the various documents is provided in Table 9. Minutes of meetings<br />
and Reviews, and progress reports in between meetings are not listed.<br />
Table 9 - Evolution of documents supporting meetings and Workshops<br />
No. Deliverable document RR PDR WS-1 CDR SIRR STRR WS-2 SVRR ORR<br />
D-01 PP Project Plan 1.0 2.0<br />
D-02 URD User Requirements Document 1.0 2.0<br />
D-03 ATDD Algorithms Theoretical Definition Document 0.5 1.0 2.0<br />
D-04 CMP Configuration Management Plan 0.5 1.0<br />
D-05 SRD System Requirements Document 0.5 1.0 2.0<br />
D-06 SDD System Design Document 0.5 1.0 2.0<br />
D-07 SIVVP System IV & V Plan 0.5 1.0<br />
D-08 SSVD System/Software <strong>Version</strong> Description 0.5 1.0<br />
D-09 SVERF System Verification File 0.5 0.6 1.0<br />
D-10 SVALF System Validation File 0.5 1.0<br />
D-11 CRD Component Requirement Document 0.5 1.0<br />
D-12 CDD Component Design Document 0.5 1.0 2.0<br />
D-13 CVERF Component Verification File 0.5 1.0 2.0<br />
D-14 ICD Interface Control Document 0.5 1.0<br />
D-15 PPR Products Prototyping Reports 1.0 2.0<br />
D-16 DOF Data Output Format 1.0 2.0<br />
D-17 REP-1 Report to the 1 st H-<strong>SAF</strong> Workshop (rolling) X<br />
D-18 REP-2 H-<strong>SAF</strong> Phase-1 Report X<br />
D-19 REP-3 H-<strong>SAF</strong> Products Validation Report (rolling) X X<br />
D-20 REP-4 H-<strong>SAF</strong> Hydrological Validation Report (rolling) X X X<br />
D-21 REP-5 Status of preparation of pre-operational products X<br />
D-22 UM User Manual 0.5 1.0<br />
D-23 FR Final Report 0.5 1.0<br />
The calendar of meetings/Reviews may be adapted to need. For instance, in preparation of the Critical<br />
Design Review (at T 0 + 24) due to authorise the release of demonstrational products, a “<strong>Version</strong>-1<br />
Check Point” (V1CP, not in Table 8) was organised 4 months in advance. Another variation to Table 8<br />
is that the CDR has been split in two sessions, a scientific-oriented one to analyse documents REP-2,<br />
PP-2.0, URD-2.0 and ATDD-1.0; and an engineering-oriented one for the remaining documents.<br />
Steering Group meetings take place at roughly 6-month intervals, generally following a Review<br />
meeting. Project Team meetings are generally organised some month before an SG meeting.<br />
Specialised meetings, for instance to coordinate product validation activities or hydrological validation<br />
activities, or for Education & Training, are organised at occasions.