H-<strong>SAF</strong> Project Plan 2.0, October 2007 - Update PP-2.2, 10 April 2008 - Chapter 3 (The coordination task) Page 44<br />

As concerns products, WP-1320 will:<br />

• establish formats, coding, protocol, etc. in such a mode that:<br />

- EUMETSAT members and cooperating States can receive the products without the need for<br />

substantial local development;<br />

- the products or part of them, depending on the EUMETSAT data policy, can be made available<br />

on the Global Telecommunication System (GTS);<br />

- the data structure is possibly the same for all communication modes (dedicated lines, via U-<br />

MARF, via EUMETCast).<br />

WP-1320 will be carried out in close cooperation with the Project Team.<br />

WP-1330: Engineering documentation<br />

The H-<strong>SAF</strong> contract with EUMETSAT implies that a number of engineering documents are presented at<br />

the Review meetings (see Tables 8 and 9), in addition to the programmatic/scientific documents to be<br />

provided under WP-1140. The list (each document to imply several issues for different Reviews) is:<br />

• Configuration Management Plan (CMP)<br />

• System Requirements Document (SRD)<br />

• Component Requirement Document (CRD)<br />

• Component Design Document (CDD)<br />

• Component Verification File (CVERF)<br />

• Interface Control Document (ICD)<br />

• System Design Document (SDD)<br />

• Products Prototyping Reports (PPR)<br />

• System IV & V Plan (SIVVP)<br />

• System/Software <strong>Version</strong> Description (SSVD)<br />

• System Verification File (SVERF)<br />

• System Validation File (SVALF)<br />

• Data Output Format (DOF).<br />

These documents come downstream of the programmatic/scientific documents produced under WP-<br />

1140, especially the URD. The Head Engineer submits draft documents or document frames to the H-<br />

<strong>SAF</strong> Participants, collects the contributions and performs editing of the documents to be delivered to the<br />

Review meetings. For those documents, he coordinates, appealing to authors of the contributions if<br />

necessary, the management of the Review Item Discrepancy (RID) associated to Review meetings.<br />

WP-1340: Control functions and Support to Project Team<br />

The purpose of WP-1340 is to support the Project Manager for ensuring configuration control, schedule<br />

control and documentation control.<br />

WP-1340 provides the Project Manager with industrial support for:<br />

• compilation and maintenance of the Configuration Management Plan;<br />

• configuration management control, that is:<br />

- configuration item identification in the general H-<strong>SAF</strong> architecture and its components, defined<br />

and developed under WP-1310, among which algorithms, models, processing chains, archives,<br />

telecommunication means (after availability of their description);<br />

- definition of procedures and guidelines for configuration control of software development, like<br />

adopted programming languages, coding, standards, protocol, etc. as stated under WP-1320;<br />

- assessment and supervision of the Configuration Management Control Function delegated to<br />

each Cluster leader;<br />

• schedule control of the activities envisaged under this Project Plan, locked to the project milestones;<br />

• configuration control of all deliverable documents listed under WP-1330 and possible others of<br />

special impact or prone to provoke updating of one or more official documents.