Exhibit No. 2.7C<br />

SHREE SHAKAMBARI FERRO ALLOYS PVT LTD.<br />

PROJECT IMPLEMENTATION SCHEDULE OF 10 MVA FERRO ALLOY PLANT WITH UTILITIES<br />

3 OF 3<br />

DESCRIPTION<br />

DAYS<br />

MONTH 1 MONTH 2 MONTH 3 MONTH 4 MONTH 5 MONTH 6 MONTH 7<br />

MONTH 8<br />

MONTH 9 MONTH 10 MONTH 11<br />

MONTH 12<br />

10 20 30 10 20 28 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30<br />

ERECTION OF DISTRIBUTION WATER LINE 50<br />

ERECTION OF POLLUTION CONTROL EQUIPMENT & BLOWER 15<br />

ERECTION OF ELECTRODE CASING 30<br />

POLLUTION CONTROL DUCTING 45<br />

EXECUTION OF REFRACTORY LINING FOR F/C SHELL 18<br />

FINAL ALIGNMENT FOR FURNACE EQUIPMENT 25<br />

ERECTION OF EOT CRANE, TELFOR AND MONORAIL HOIST 15<br />

ERECTION OF CHARGING BINS AND CHUTES 25<br />

EXECUTION OF PASTING WORKS FOR FURNACE SHELL 20<br />

TRAIL RUN FOR LT MOTORS 7<br />

TESTING AND COMMISSIONING OF FURNACE 7<br />

TESTING AND COMMISSIONING OF RMHS CIRCUIT 10<br />

TESTING AND COMMISSIONING OF PUMP HOUSE 5<br />

FURNACE PREHEATING 7