CHAPTER-2<br />
EIA/EMP OF Shree Shakambari Ferro Alloys <strong>Pvt</strong>. <strong>Ltd</strong>.<br />
conditioned with ductable package air conditioners, which will be located in a<br />
plant A.C. room, adjacent to the control room.<br />
Ventilation System:<br />
The ventilation requirement for various area in the Turbo generator building<br />
in CPP can be broadly classified under two section:<br />
i. Area which need positive pressure to avoid outside air infiltration,<br />
which is to be achieved by continuous fresh supply.<br />
ii.<br />
Area which need exhaust ventilation and have adjacent sufficiently<br />
large wall to fix exhaust fans.<br />
Fire Protection System<br />
The fire protection system for the proposed CPP shall be consisting of :<br />
Hydrant System for all the areas of the plant.<br />
High velocity water spray system for Transformers<br />
Automatic fire detection and alarm system<br />
Manual fire alarm system<br />
Portable fire Extinguishers<br />
The components of the fire protection system, wherever applicable shall be BIS<br />
marked /TAC approved type. The system shall be designed based on safety<br />
requirements and generally conforming to Tariff Advisory Committee (TAC)<br />
regulations, and National Fire Protection Association of America.<br />
Portable type fire extinguishers of DCP type shall be located in the TG building,<br />
control room, MCC rooms fire pump house etc.<br />