CHAPTER-2<br />
EIA/EMP OF Shree Shakambari Ferro Alloys <strong>Pvt</strong>. <strong>Ltd</strong>.<br />
2.18.2 Details of work force<br />
TableNo.2.3<br />
S.No Description of Work<br />
Duration No of workers<br />
of work<br />
1 Civil buildings, …………… ……………<br />
Plant foundations<br />
2 Road & drainage …………… ……………<br />
works<br />
3 Furnace building, 12 months 30<br />
Raw<br />
Material handling<br />
system<br />
& other sheds<br />
4 Fabrication & 5 months 20<br />
erection<br />
Of Furnace<br />
5 Electrical Installation 2 months 15<br />
A. Ferro alloy & Ferro Silicon Plant:<br />
Ferro alloy & Ferro Silicon will operate for 3 shifts. The manpower<br />
deployment will be 107 during operational phase.<br />
B) Captive Power Plant:<br />
The plant will operate for 3 shifts. The manpower deployment will be 125<br />
during operational phase.<br />
The total technical executives required are around …….. and technical<br />
manpower will be ……. The manpower required during implementation phase<br />
will be …….<br />