an <strong>MRL</strong> Plan as a formal Contract Data Requirements List (CDRL). Althougha Data Item Description (DID) does not exist for an <strong>MRL</strong> plan, generic DIDsare available, such as for technical reports.If MMPs are being generated as a result of maturity shortfalls, the programoffice needs to determine if they need these plans to be deliverable items.Preferably, the MMPs may be documented as part of the program’s normalRisk Management process, which should include documented risk mitigationplans, which may or may not be deliverable. Alternatively, MMPs may beincluded in the SOW as a formal CDRL. Once again there is no dedicatedDID for MMPs, but generic technical report DIDs may be acceptable.6-5