Autumn
PDF6S05 - 2011Download - Clancy Docwra
PDF6S05 - 2011Download - Clancy Docwra
- No tags were found...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
| STRONG |<br />
On track for Rail<br />
Acton Town to Chiswick Park<br />
Embankment Stabilisation<br />
This recently completed scheme<br />
for LUL, with a value of c £2.5m,<br />
required a number of solutions<br />
at 5 separate locations between two<br />
stations on the District Line.<br />
The first 3 locations were<br />
undertaken during two weekend<br />
track possessions utilising road/rail<br />
plant to install 161 5 metre driven<br />
steel piles infilled with 1100 concrete<br />
planks, the void between the track<br />
and the new structure was raised<br />
with 250 tonnes of compacted gravel<br />
wrapped in a geo textile membrane; a<br />
new trackside walkway and safety<br />
handrail completed the works.<br />
The next two locations were<br />
undertaken during traffic hours as<br />
access, whilst restricted, was<br />
possible from the highway, a partial<br />
road closure allowed scaffold access<br />
to the failing embankments, which<br />
were in a confined area between the<br />
track and local residences. A reduced<br />
dig operation was undertaken at<br />
both locations, each of which were<br />
accessed from a single entry point,<br />
removing 1250 tonnes of spoil and<br />
installing temporary works to<br />
support the adjacent track prior to<br />
reconstruction of the embankments.<br />
The LUL design had specified the<br />
raising of the existing lower<br />
retaining wall by 1.7m and a revised<br />
profile created using a new<br />
proprietary system Ram Wall. This<br />
comprises of a galvanised steel grid<br />
installed and fixed in sections to an<br />
agreed pattern to give structural<br />
strength, infilled with a lightweight<br />
Maxit aggregate which reduced the<br />
loadings on the higher embankment<br />
compared to traditional fill<br />
materials. Over 1400m 3 of Ram Wall<br />
and 1900m 3 of Maxit were installed<br />
over the 280m length of the two<br />
sites, making it the largest scheme<br />
built using the system.<br />
The structures were capped with<br />
150mm of seeded topsoil, with a new<br />
walkway and safety handrail<br />
installed.<br />
During the construction of these<br />
works Clancy Docwra tendered for,<br />
and has been awarded, a 5 year<br />
framework for earthworks and<br />
embankment stabilisation with LUL.<br />
Gants Hill Ventilation<br />
Shafts VP50 &VP50a<br />
One of many ventilation shafts on<br />
the LUL Central Line, Shafts<br />
VP50 and VP50a surface at a<br />
roundabout on the busy A12 trunk<br />
road. Both brick built structures had<br />
been identified as having defective<br />
steelwork supporting the safety grills<br />
protecting the opening.<br />
Scaffolding was erected under TfL<br />
traffic management incorporating a<br />
birdcage deck enabling access to the<br />
defective steel and to protect the<br />
track below.<br />
Safety grills to VP50a were removed<br />
and all supporting steelwork to the<br />
5metre diameter shaft was prepared<br />
and repainted using a three coat<br />
system, prior to the reinstalling and<br />
securing the grills<br />
Shaft VP50 was a smaller rectangular<br />
shaft over a machine room not the<br />
track, but requiring equal protection<br />
and a different solution. The lighter<br />
steel work supporting the safety grill<br />
had deteriorated to the point where<br />
replacement was required; following<br />
the strip out of the old structure new<br />
galvanised steelwork was manufactured<br />
and installed to include new safety grills.<br />
Project Manager Mark Driscoll<br />
confirmed that the project with a<br />
value of £28k, which was secured as<br />
part of £1.6m package awarded under<br />
the LUL Civils Lot B Framework, has<br />
progressed well and to the<br />
satisfaction of both LUL and Tfl.<br />
14 | <strong>Autumn</strong> Issue