31.08.2015 Views

Autumn

PDF6S05 - 2011Download - Clancy Docwra

PDF6S05 - 2011Download - Clancy Docwra

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

| STRONG |<br />

On track for Rail<br />

Acton Town to Chiswick Park<br />

Embankment Stabilisation<br />

This recently completed scheme<br />

for LUL, with a value of c £2.5m,<br />

required a number of solutions<br />

at 5 separate locations between two<br />

stations on the District Line.<br />

The first 3 locations were<br />

undertaken during two weekend<br />

track possessions utilising road/rail<br />

plant to install 161 5 metre driven<br />

steel piles infilled with 1100 concrete<br />

planks, the void between the track<br />

and the new structure was raised<br />

with 250 tonnes of compacted gravel<br />

wrapped in a geo textile membrane; a<br />

new trackside walkway and safety<br />

handrail completed the works.<br />

The next two locations were<br />

undertaken during traffic hours as<br />

access, whilst restricted, was<br />

possible from the highway, a partial<br />

road closure allowed scaffold access<br />

to the failing embankments, which<br />

were in a confined area between the<br />

track and local residences. A reduced<br />

dig operation was undertaken at<br />

both locations, each of which were<br />

accessed from a single entry point,<br />

removing 1250 tonnes of spoil and<br />

installing temporary works to<br />

support the adjacent track prior to<br />

reconstruction of the embankments.<br />

The LUL design had specified the<br />

raising of the existing lower<br />

retaining wall by 1.7m and a revised<br />

profile created using a new<br />

proprietary system Ram Wall. This<br />

comprises of a galvanised steel grid<br />

installed and fixed in sections to an<br />

agreed pattern to give structural<br />

strength, infilled with a lightweight<br />

Maxit aggregate which reduced the<br />

loadings on the higher embankment<br />

compared to traditional fill<br />

materials. Over 1400m 3 of Ram Wall<br />

and 1900m 3 of Maxit were installed<br />

over the 280m length of the two<br />

sites, making it the largest scheme<br />

built using the system.<br />

The structures were capped with<br />

150mm of seeded topsoil, with a new<br />

walkway and safety handrail<br />

installed.<br />

During the construction of these<br />

works Clancy Docwra tendered for,<br />

and has been awarded, a 5 year<br />

framework for earthworks and<br />

embankment stabilisation with LUL.<br />

Gants Hill Ventilation<br />

Shafts VP50 &VP50a<br />

One of many ventilation shafts on<br />

the LUL Central Line, Shafts<br />

VP50 and VP50a surface at a<br />

roundabout on the busy A12 trunk<br />

road. Both brick built structures had<br />

been identified as having defective<br />

steelwork supporting the safety grills<br />

protecting the opening.<br />

Scaffolding was erected under TfL<br />

traffic management incorporating a<br />

birdcage deck enabling access to the<br />

defective steel and to protect the<br />

track below.<br />

Safety grills to VP50a were removed<br />

and all supporting steelwork to the<br />

5metre diameter shaft was prepared<br />

and repainted using a three coat<br />

system, prior to the reinstalling and<br />

securing the grills<br />

Shaft VP50 was a smaller rectangular<br />

shaft over a machine room not the<br />

track, but requiring equal protection<br />

and a different solution. The lighter<br />

steel work supporting the safety grill<br />

had deteriorated to the point where<br />

replacement was required; following<br />

the strip out of the old structure new<br />

galvanised steelwork was manufactured<br />

and installed to include new safety grills.<br />

Project Manager Mark Driscoll<br />

confirmed that the project with a<br />

value of £28k, which was secured as<br />

part of £1.6m package awarded under<br />

the LUL Civils Lot B Framework, has<br />

progressed well and to the<br />

satisfaction of both LUL and Tfl.<br />

14 | <strong>Autumn</strong> Issue

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!