The following distances in mm’s should<br />
be observed<br />
200 below guttering or eaves<br />
the 25mm separation distance should be<br />
measured from the outside surface of the<br />
inner liner.<br />
300 from corners or openings (windows<br />
doors etc) and from other horizontal<br />
terminals on same wall<br />
1200 from a facing surface<br />
1500 from another terminal vertically on the<br />
same wall<br />
2000 from ground level<br />
The materials from which the flue is<br />
constructed must be non-combustible,<br />
resistant to internal and external corrosion,<br />
and be capable of withstanding the stresses<br />
and loadings associated with normal use.<br />
When designing the flue system the<br />
prevention of the formation and entrapment<br />
of condensation must be a key<br />
consideration.<br />
Horizontal flue should be fitted ensuring a<br />
slight gradient approx 2 0 towards the<br />
terminal Where condensation is unavoidable<br />
traps should be included to encourage the<br />
condensates to flow freely to a point from<br />
which they may be released, preferably into<br />
a gully.<br />
The condensate pipe from the flue to the<br />
disposal point must be made from corrosion<br />
resistant pipe of not less than 25mm internal<br />
diameter.<br />
If the flue passes through a wall, ceiling, or<br />
roof made from combustible material then it<br />
has to be sleeved so as to provide a<br />
minimum of a 25mm void between the<br />
exterior of the flue and the internal wall of<br />
the sleeve.<br />
For double wall flue pipe conforming to<br />
BS 4543-2 and 3 the external skin and air<br />
gap constitutes insulation to a standard<br />
where no extra clearance from combustible<br />
material is required other than normal<br />
installation tolerances<br />
Double walled pipe conforming to BS 715<br />
14