In Situ Francis Turbine Blade Replacement due to Gross Cavitation
In Situ Francis Turbine Blade Replacement due to Gross Cavitation
In Situ Francis Turbine Blade Replacement due to Gross Cavitation
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Project Facts and His<strong>to</strong>ry<br />
• Pointe du Bois, Mani<strong>to</strong>ba, Canada – Approximately 95 miles<br />
(150 kilometers) North East of Winnipeg, Mani<strong>to</strong>ba, Canada<br />
• On the Winnipeg River<br />
• First Unit in Service: 1911<br />
• Construction Completed: 1926<br />
• Construction Cost: $3.25 Million<br />
• Station Capacity: 78 MW<br />
• Average Annual Generation: 599 kWh<br />
• Waterfall Drop: 45 feet (14 Meters)<br />
• Powerhouse Length: 440 feet (135 Meters)<br />
• <strong>Turbine</strong> Genera<strong>to</strong>rs: 15 Double horizontal shaft <strong>Francis</strong><br />
<strong>Turbine</strong> Camelback units and 1 Straflo unit<br />
• Project Acquired by Mani<strong>to</strong>ba Hydro in 2002<br />
<strong>In</strong> <strong>Situ</strong> <strong>Francis</strong> turbine <strong>Blade</strong> <strong>Replacement</strong> | NWHA Hood River| 2013-05-23<br />