NEW FACTORY FOR PRODUCTION OF FORKLIFT TRUCKS<br />
Performance Surface : 18.707 m²<br />
Year of implementation : 2006<br />
Execution time :<br />
6months<br />
Construction of new factory for the production of forklift trucks in the Besaya Business Park, in<br />
the municipality of Reocín.<br />
The installation is carried out on a plot of 62.905 m² and has been required the excavation of<br />
some 20,000 m³ of Earth.<br />
It is divided into 2 ships of steel structure of straight columns 81 and recessed, Gable with three<br />
intermediate pillars of dimensions 211 and 101 meters long and 16 meters wide, with a height<br />
to the eaves of 9 meters and height of 8 meters. Slope of 10% cover. With a modulation of 12<br />
and10meterslongitudinalandtransverse20and16meters.2bridgescrane10Tn,15meters<br />
wide and tour of 54 meters and 1 bridge crane 5 tons, 12 meters wide and 60 meters.<br />
The roof is formed by enclosure type "in‐situ" sandwich hiding straps.<br />
Factory production of forklift trucks for Haulotte in the Business Park Besaya (Cantabria).