3.- Industrial building
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Catalogue<br />
<strong>Industrial</strong> Construction<br />
PLANTA DE GENERACIÓN ELÉCTRICA CON BIOMASA<br />
Performance Surface : 18.708 m²<br />
Year of implementation 2010<br />
Execution time :<br />
12 months<br />
Construction of new plant based on the production of electricity from energy recovery by combustion<br />
of biomass of forest origin. These wastes are burned in the biomass boiler by transferring heat to the<br />
water that turns into steam to drive a turbine coupled to an alternator whose purpose is the<br />
production of electricity.<br />
The plant was built on a plot of 11<strong>3.</strong>45, 49 m² in the Besaya Business Park of Reocín. In this plot, the<br />
space dedicated to the plant is 18.708 m², of which 1,100 m² will be built‐up area and 3,800 m²<br />
surface corresponding to facilities.<br />
The various <strong>building</strong>s that make up the biomass plant are:<br />
• Turbine <strong>building</strong>,<br />
• Biomass storage silo,<br />
• Buildings boiler and electric,<br />
• Waste and water treatment <strong>building</strong>s,<br />
• Electrical substation,<br />
• Screening,<br />
• Building of reception and processing of biomass.<br />
Power plant with biomass in the Business Park Besaya (Cantabria).