22.07.2016 Views

Interactive PDF

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Construction Regulations |31<br />

law |61<br />

The Construction<br />

(Design and Management)<br />

Regulations (Northern Ireland) 2016<br />

Key tips to avoid the<br />

pitfalls of termination<br />

By Anna McClimonds, Solicitor, Cleaver Fulton Rankin’.<br />

The Construction (Design<br />

and Management)<br />

been raised. Namely, a project is<br />

notifiable if the construction work<br />

BY AnnA McCliMonds, soliCitor,<br />

Regulations (Northern is CleAver scheduled Fulton last longer rAnkin than 30<br />

Ireland) 2016 are due working days and have more than<br />

Construction to come into operation contracts 1. 20 Whether workers you simultaneously have a right toor if it<br />

on 1 August often include 2016 and exceeds terminate 500 in person the circumstances days; and<br />

will revoke a termination the 2007<br />

whether the circumstances you are<br />

provision Regulations. allowing parties The relying exemption upon can from be proved. client duties<br />

to terminate a contract for domestic clients has been<br />

in The certain 2016 CDM circumstances<br />

Regulations are 2. removed; Ensure your and right to terminate<br />

by intended giving to protect written persons notice. from The exists Approved at the time Code you of issue Practice the<br />

Alongside health and safety a contractual risks arising is termination replaced with notice straightforward<br />

and the other<br />

right from construction to terminate, work the through guidance. party has not remedied its default.<br />

parties the establishment also have of a a systematic<br />

common framework law for managing right to risk. They 3. For Compliance the purposes with all of requirements the CDM<br />

terminate are intended for to be repudiatory shorter and Regulations, set out in the the contract. following key<br />

breach substantially i.e. simpler a sufficiently in structure questions should be considered<br />

serious than the 2007 breach Regulations of contract and will 4. at Caution the commencement must be taken where of any<br />

or place demonstrating greater obligations an in respect construction there is a two work: stage notice<br />

intention of health and not safety to be on bound those for<br />

by whom the a contract. project is carried out and<br />

also The their 2013 design High Court and construction case of<br />

Vivergo team. Fuels Ltd v Redhall Engineering<br />

Solutions Ltd [2013] EWHC 4030<br />

(TCC) The key highlights changes the problems a<br />

party implemented can face when by exercising the 2016<br />

its CDM right to Regulations terminate. In particular, are:<br />

it deals with the situation where<br />

another The Regulations party challenges will apply the validity to all<br />

procedure to ensure the notices<br />

Do are the connected works in fall both within content and the<br />

definition time. of “construction<br />

work”?<br />

5. The notice must be clear and<br />

“Construction unambiguous. Consider work” is the broadly<br />

defined following under when Regulation drafting a notice: 2(1) as<br />

“the carrying out of any building,<br />

• civil Title engineering the document or as engineering a notice,<br />

construction although a letter works”, may with suffice specific as a<br />

to every designer and contractor<br />

appointed, or being considered for<br />

appointment;<br />

Ensuring that:<br />

the contractor (if there is only<br />

Pursuant to Regulation 5, where<br />

there is more than one contractor<br />

working on a project at any<br />

one time, or if it is reasonably<br />

foreseeable there will be more<br />

than one, the client is required<br />

of clients a termination of construction notice and projects, claims examples warning notice of such in works certain provided. one) or the principal contractor to appoint in writing as soon as<br />

that whether termination or not a person is itself a is acting circumstances.<br />

draws up a construction phase reasonably practicable, and in any<br />

repudiatory in the course breach of or entitling furtherance them of Who is the “client” and plan before the construction event, before the construction<br />

to a business; terminate the contract and claim • what Specifically are state its duties? in the notice that it<br />

phase begins;<br />

phase begins:<br />

damages.<br />

is intended to be a warning/<br />

A designer with control over<br />

The The CDM basic co-ordinator rule for service role of has “Client” termination is defined notice; as and “any person the principal designer prepares the pre-construction phase as<br />

a been termination removed, notice with is that various all duties for whom a project is carried a health and safety file for the principal designer; and<br />

contractual recast, including requirements client duties must and • out”, Refer with to the Regulation contractual 4 providing clause the<br />

project.<br />

A contractor as principal<br />

be general strictly duties; complied with. As Lord for notice the specific is given under client and duties. mirror These<br />

Taking reasonable steps to ensure contractor.<br />

Hoffman said in Mannai Investments include: the wording of that clause.<br />

that the principal contractor and<br />

Co The Ltd client v Eagle is required Star Assurance to appoint “If the<br />

principal designer comply with Is the project notifiable?<br />

clause a principal had said designer that the as notice well as had Making In terms suitable of interpreting arrangements notices, for against the relevant background • Immaterial errors will be ignored if<br />

to any relevant duties stated in<br />

a principal be on blue contractor paper, it would in any have the managing following a project, principles including laid down the or context known to both<br />

Regulations 11 to 14.<br />

Pursuant the notice to unambiguously Regulation 6, a delivers project<br />

been project no where good serving there a is, notice or it on in<br />

is allocation Vivergo Fuels of sufficient v Redhall Engineering time and parties.<br />

is notifiable the purpose; to and the Executive in<br />

pink<br />

reasonably<br />

paper, however<br />

foreseeable<br />

clear it<br />

that<br />

might Solutions<br />

there resources;<br />

Ltd should be considered:<br />

writing as soon as practicable<br />

have Regulation 8 also provides further<br />

will be,<br />

been<br />

more<br />

that<br />

than<br />

the [party]<br />

one contractor<br />

wanted to<br />

• The notice must be sufficiently before • In the the context construction of clauses phase which<br />

terminate.”<br />

• general health and safety duties<br />

working on the project;<br />

Ensuring<br />

Unilateral<br />

the<br />

notices<br />

above<br />

are<br />

arrangements<br />

to be<br />

clear and unambiguous and leave<br />

begins require if the a warning construction notice followed work<br />

The following points should be interpreted in the same way as and roles.<br />

are maintained and reviewed the receiver in no reasonable<br />

lasts<br />

by<br />

longer<br />

a termination<br />

than 30<br />

notice,<br />

working<br />

the two<br />

days<br />

considered before exercising a right contractual documents. That is, they<br />

The duty to notify a project throughout the project;<br />

doubt as to how and when the<br />

and<br />

notices<br />

has more<br />

must be<br />

than<br />

connected<br />

20 workers<br />

both in<br />

to terminate:<br />

are to be looked at objectively,<br />

now lies with the client and the Providing pre-construction<br />

Does notice a is principal intended to designer operate.<br />

working<br />

content<br />

simultaneously,<br />

and time.<br />

or exceed<br />

threshold for notification has information as soon as practicable<br />

and principal contractor<br />

500 person days.<br />

need to be appointed?<br />

Cleaver Fulton Rankin’s market-leading team of lawyers deliver comprehensive commercial and<br />

practical advice, designed to achieve the most cost efficient result, to a diverse range of corporate<br />

clients. The Construction Team at Cleaver Fulton Rankin specialises in providing advice across the<br />

spectrum of non-contentious matters such as drafting and advising on building contracts, appointments,<br />

bonds, novation agreements and collateral warranties.<br />

If you would like further information or to find out how we can help you please give us a<br />

call on: 028 9024 3141 or visit our website: www.cfrlaw.co.uk

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!