You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Construction Regulations |31<br />
law |61<br />
The Construction<br />
(Design and Management)<br />
Regulations (Northern Ireland) 2016<br />
Key tips to avoid the<br />
pitfalls of termination<br />
By Anna McClimonds, Solicitor, Cleaver Fulton Rankin’.<br />
The Construction (Design<br />
and Management)<br />
been raised. Namely, a project is<br />
notifiable if the construction work<br />
BY AnnA McCliMonds, soliCitor,<br />
Regulations (Northern is CleAver scheduled Fulton last longer rAnkin than 30<br />
Ireland) 2016 are due working days and have more than<br />
Construction to come into operation contracts 1. 20 Whether workers you simultaneously have a right toor if it<br />
on 1 August often include 2016 and exceeds terminate 500 in person the circumstances days; and<br />
will revoke a termination the 2007<br />
whether the circumstances you are<br />
provision Regulations. allowing parties The relying exemption upon can from be proved. client duties<br />
to terminate a contract for domestic clients has been<br />
in The certain 2016 CDM circumstances<br />
Regulations are 2. removed; Ensure your and right to terminate<br />
by intended giving to protect written persons notice. from The exists Approved at the time Code you of issue Practice the<br />
Alongside health and safety a contractual risks arising is termination replaced with notice straightforward<br />
and the other<br />
right from construction to terminate, work the through guidance. party has not remedied its default.<br />
parties the establishment also have of a a systematic<br />
common framework law for managing right to risk. They 3. For Compliance the purposes with all of requirements the CDM<br />
terminate are intended for to be repudiatory shorter and Regulations, set out in the the contract. following key<br />
breach substantially i.e. simpler a sufficiently in structure questions should be considered<br />
serious than the 2007 breach Regulations of contract and will 4. at Caution the commencement must be taken where of any<br />
or place demonstrating greater obligations an in respect construction there is a two work: stage notice<br />
intention of health and not safety to be on bound those for<br />
by whom the a contract. project is carried out and<br />
also The their 2013 design High Court and construction case of<br />
Vivergo team. Fuels Ltd v Redhall Engineering<br />
Solutions Ltd [2013] EWHC 4030<br />
(TCC) The key highlights changes the problems a<br />
party implemented can face when by exercising the 2016<br />
its CDM right to Regulations terminate. In particular, are:<br />
it deals with the situation where<br />
another The Regulations party challenges will apply the validity to all<br />
procedure to ensure the notices<br />
Do are the connected works in fall both within content and the<br />
definition time. of “construction<br />
work”?<br />
5. The notice must be clear and<br />
“Construction unambiguous. Consider work” is the broadly<br />
defined following under when Regulation drafting a notice: 2(1) as<br />
“the carrying out of any building,<br />
• civil Title engineering the document or as engineering a notice,<br />
construction although a letter works”, may with suffice specific as a<br />
to every designer and contractor<br />
appointed, or being considered for<br />
appointment;<br />
Ensuring that:<br />
the contractor (if there is only<br />
Pursuant to Regulation 5, where<br />
there is more than one contractor<br />
working on a project at any<br />
one time, or if it is reasonably<br />
foreseeable there will be more<br />
than one, the client is required<br />
of clients a termination of construction notice and projects, claims examples warning notice of such in works certain provided. one) or the principal contractor to appoint in writing as soon as<br />
that whether termination or not a person is itself a is acting circumstances.<br />
draws up a construction phase reasonably practicable, and in any<br />
repudiatory in the course breach of or entitling furtherance them of Who is the “client” and plan before the construction event, before the construction<br />
to a business; terminate the contract and claim • what Specifically are state its duties? in the notice that it<br />
phase begins;<br />
phase begins:<br />
damages.<br />
is intended to be a warning/<br />
A designer with control over<br />
The The CDM basic co-ordinator rule for service role of has “Client” termination is defined notice; as and “any person the principal designer prepares the pre-construction phase as<br />
a been termination removed, notice with is that various all duties for whom a project is carried a health and safety file for the principal designer; and<br />
contractual recast, including requirements client duties must and • out”, Refer with to the Regulation contractual 4 providing clause the<br />
project.<br />
A contractor as principal<br />
be general strictly duties; complied with. As Lord for notice the specific is given under client and duties. mirror These<br />
Taking reasonable steps to ensure contractor.<br />
Hoffman said in Mannai Investments include: the wording of that clause.<br />
that the principal contractor and<br />
Co The Ltd client v Eagle is required Star Assurance to appoint “If the<br />
principal designer comply with Is the project notifiable?<br />
clause a principal had said designer that the as notice well as had Making In terms suitable of interpreting arrangements notices, for against the relevant background • Immaterial errors will be ignored if<br />
to any relevant duties stated in<br />
a principal be on blue contractor paper, it would in any have the managing following a project, principles including laid down the or context known to both<br />
Regulations 11 to 14.<br />
Pursuant the notice to unambiguously Regulation 6, a delivers project<br />
been project no where good serving there a is, notice or it on in<br />
is allocation Vivergo Fuels of sufficient v Redhall Engineering time and parties.<br />
is notifiable the purpose; to and the Executive in<br />
pink<br />
reasonably<br />
paper, however<br />
foreseeable<br />
clear it<br />
that<br />
might Solutions<br />
there resources;<br />
Ltd should be considered:<br />
writing as soon as practicable<br />
have Regulation 8 also provides further<br />
will be,<br />
been<br />
more<br />
that<br />
than<br />
the [party]<br />
one contractor<br />
wanted to<br />
• The notice must be sufficiently before • In the the context construction of clauses phase which<br />
terminate.”<br />
• general health and safety duties<br />
working on the project;<br />
Ensuring<br />
Unilateral<br />
the<br />
notices<br />
above<br />
are<br />
arrangements<br />
to be<br />
clear and unambiguous and leave<br />
begins require if the a warning construction notice followed work<br />
The following points should be interpreted in the same way as and roles.<br />
are maintained and reviewed the receiver in no reasonable<br />
lasts<br />
by<br />
longer<br />
a termination<br />
than 30<br />
notice,<br />
working<br />
the two<br />
days<br />
considered before exercising a right contractual documents. That is, they<br />
The duty to notify a project throughout the project;<br />
doubt as to how and when the<br />
and<br />
notices<br />
has more<br />
must be<br />
than<br />
connected<br />
20 workers<br />
both in<br />
to terminate:<br />
are to be looked at objectively,<br />
now lies with the client and the Providing pre-construction<br />
Does notice a is principal intended to designer operate.<br />
working<br />
content<br />
simultaneously,<br />
and time.<br />
or exceed<br />
threshold for notification has information as soon as practicable<br />
and principal contractor<br />
500 person days.<br />
need to be appointed?<br />
Cleaver Fulton Rankin’s market-leading team of lawyers deliver comprehensive commercial and<br />
practical advice, designed to achieve the most cost efficient result, to a diverse range of corporate<br />
clients. The Construction Team at Cleaver Fulton Rankin specialises in providing advice across the<br />
spectrum of non-contentious matters such as drafting and advising on building contracts, appointments,<br />
bonds, novation agreements and collateral warranties.<br />
If you would like further information or to find out how we can help you please give us a<br />
call on: 028 9024 3141 or visit our website: www.cfrlaw.co.uk