In my opinion<br />

The challenge of the conversion<br />

The Conservative Government has an ambitious programme to open over 600 new Free Schools by 2020 and has established<br />

the LocatED property company, to secure the sites across the UK. Nicolas Maari, Head of Architecture at Pellings, thinks that<br />

whilst this is laudable, the quality of children’s education should not be compromised in the rush to provide for increased<br />

pupil numbers.<br />

The dilemma is that in built up<br />

urban areas there aren’t the<br />

large tracts of land available<br />

to build the schools that tick all the<br />

quality criteria. Multi Academy<br />

School Trusts are therefore<br />

sometimes being requested to<br />

use existing buildings – old<br />

office blocks, factories or<br />

hospitals, perhaps.<br />

The main issue with converting<br />

these buildings to schools is on space<br />

standards and the clustering of year<br />

groups, which wherever possible shouldn’t<br />

be compromised for the sake of the children’s<br />

education/teaching.<br />

So, for example, if there is a school with a<br />

two-form entry in one year then ideally one<br />

wants to group those year groups as well as<br />

ancillary accommodation. This often proves<br />

difficult within a building conversion.<br />

Having previously worked on projects where<br />

schools were accommodated in multi-storey<br />

office buildings, issues we came up against<br />

were fitting the ancillary space to service the<br />

year groups. In that instance we had to<br />

consider splitting the year groups as well as<br />

staggering playtimes and lunches. This in<br />

turn would affect the operation of the school.<br />

In addition, it is difficult to achieve the same<br />

efficiencies in spaces and operation that are<br />

possible in building a new school from<br />

scratch. Adapting buildings previously used<br />

as residential accommodation may result in<br />

schools being single aspect with corridors<br />

taking up space on external walls. This<br />

typically would be mitigated when<br />

developing a new build school in order to<br />

obtain efficiencies in the useable area.<br />

of the age of the<br />

building and its<br />

low ceilings. The<br />

minimum<br />

requirement<br />

should be at<br />

least 2.7<br />

metres clear<br />

to get the<br />

light to the<br />

back of the<br />

classroom and<br />

meet Building<br />

Bulletin regulations.<br />

This was not possible in<br />

this building, and as such this building which<br />

was earmarked for conversion to a school<br />

needed to be demolished, which significantly<br />

affected the programme of delivering this free<br />

school. This requirement is typically very<br />

difficult to achieve when converting a<br />

residential building into a school. This,<br />

however, is more achievable in office building<br />

conversions.<br />

Nicolas Maari<br />

Dealing with buildings with totally different<br />

types of structure can be a challenge. What if<br />

there are structural columns in the middle of<br />

classrooms? To remove these to achieve clear<br />

classroom/studio and hall spaces could be<br />

very costly to alter, and perhaps life cycle<br />

costs can be just as expensive as building a<br />

new school.<br />

Managing buildings and spaces are more<br />

complex with existing buildings. In an urban<br />

area where the only option is to have a rooftop<br />

playground then there is the logistics<br />

issue of staggering play-time and supervising<br />

it.<br />

Controversially, The Education Skills Funding<br />

Authority has moved away from the hard and<br />

fast ethos of providing play spaces on-site. It<br />

used to be very strict but is now more flexible<br />

in a priority classification, and where<br />

unavoidable is prepared to allow provision of<br />

off-site play areas.<br />

Many educationalists would argue that in<br />

terms of well-being it is important for city<br />

children to have external play space.<br />

However, because of the number of pupil<br />

places required this seems to no longer be a<br />

priority, although arguably this is to the<br />

detriment of the wellbeing of the pupils.<br />

Flexibility is now the name of the game and<br />

politically the pressure is on for the existing<br />

administration to deliver the school places. In<br />

the days when Local Education Authorities<br />

were setting minimum standards it was clear<br />

what had to be delivered. With academies it is<br />

less clear and it is down to the professional<br />

advisors to work with the academy providers<br />

to recognise the importance of those<br />

standards.<br />

www.pellings.co.uk<br />

The previous use of the building needs to be<br />

considered from the outset before embarking<br />

on converting it to a school building. We have<br />

found, for example, that invariably, the<br />

acoustics don’t meet the needs of the school<br />

use, and with constrained window sizes the<br />

natural lighting in an existing building is often<br />

not adequate for school use.<br />

This was the case with an old manor building<br />

which I was previously involved in. The floor<br />

to ceiling heights were constrained because<br />

Winter 2018 <strong>4152</strong> 27