5-acre<br />

100 units per acre (Table 3).<br />

ITEM<br />

QUANTITY<br />

COST<br />

PER UNIT<br />

TOTAL COST<br />

Gross Development Value (GDV) 500 units RM250,000 RM125,000,000<br />

Land cost<br />

5 acres *RM110 per ft 2 RM23,958,000<br />

<strong>Building</strong> Cost<br />

- Apartments 450,000ft 2 *RM95 per ft 2 RM42,750,000<br />

- Podium car park 1,050 bays *RM18,000 per bay RM18,900,000<br />

Total <strong>Building</strong> Cost<br />

RM61,650,000<br />

Infrastructure Cost<br />

- Road, drainage, services road 5 acres *RM1,000,000 per acre RM5,000,000<br />

- Landscape 5 acres *RM650,000 per acre RM3,250,000<br />

- Upgrading cost for traffic<br />

disbursement<br />

- - *RM1,000,000<br />

Facilities Cost<br />

- TNB sub-station 1 no. *RM150,000 RM150,000<br />

- Refuse chamber 1 no. *RM80,000 RM80,000<br />

- Surau 1 no. *RM50,000 RM50,000<br />

- Guard house 1 no. *RM60,000 RM60,000<br />

Total Facilities Cost RM340,000<br />

Capital Contributions & Compliance Costs<br />

- Land conversion premium<br />

- (Agriculture to residential)<br />

15% of<br />

market value<br />

Total Infrastructure Cost<br />

RM110 per ft 2<br />

- Development order/Planning fees 500 units RM50 RM25,000<br />

- <strong>Building</strong> plan & Infra fees 500 units RM150 RM75,000<br />

- Survey fees 5 acres RM5,000 RM25,000<br />

- Strata title application 500 units RM1,200 RM600,000<br />

RM500<br />

- ISF contribution – road 450,000 ft 2 (for every 1,000ft 2 )<br />

RM225,000<br />

- ISF contribution – drainage 5 acres RM5,000 RM25,000<br />

- Development charges - 1.5% of GDV RM1,875,000<br />

- Contribution to TNB 500 units RM450 RM225,000<br />

- Contribution to IWK - 1.0% of GDV RM1,250,000<br />

- Contribution to SYABAS<br />

– residential<br />

- 0.25% of GDV RM312,500<br />

Total Capital Contributions & Compliance Costs RM8,231,200<br />

Other Soft Costs<br />

- Professional fees<br />

- *6% of Construction Cost RM4,768,272<br />

- Sales & marketing &<br />

administration cost<br />

- *1.5% of GDV RM1,875,000<br />

Total Soft Cost RM6,643,272<br />

(*Estimation is made based on common practice and market price)<br />

Table 3: Breakdown of development cost for an average standard apartment.<br />

RM9,250,000<br />

RM3,593,700<br />

<br />

is RM8,231,200 or 6.6%The Total<br />

<br />

RM79,471,200; couple with Land<br />

Cost (RM23,958,000) and (RM6,643,272) can result a total of RM110,072,472<br />

or 88%<br />

<strong>Building</strong> & <strong>Investment</strong> | www.b-i.biz 37