(iv) Petrochemical Complex<br />
Government of India Commitment:<br />
Section 93 – Schedule 13 –<br />
Infrastructure item 4.<br />
“4. IOC or HPCL shall, within six<br />
months from the appointed day,<br />
examine the feasibility of establishing<br />
a greenfield crude oil refinery and<br />
petrochemical complex in the<br />
successor State of Andhra Pradesh<br />
and take an expeditious decision<br />
thereon;”<br />
Government of Andhra Pradesh (Go<strong>AP</strong>), GAIL<br />
India Limited (GAIL) and HPCL signed a MoU<br />
on 27 January 2017 at Vishakhapatnam for<br />
the Petrochemical Complex with an estimated<br />
cost of Rs. 32,901 Crore at Kakinada, Andhra<br />
Pradesh. Feasibility study has been<br />
carried out for the Petrochemical Complex.<br />
Oil PSUs have indicated to the Government of<br />
Andhra Pradesh that Viability Gap Funding<br />
(VGF) is necessary to make the project viable.<br />
12,13. The Union Home Secretary, on 12<br />
March 2018 has directed that the matter of<br />
VGF be taken up with the Ministry of Finance;<br />
the issue is still pending.<br />
Status <strong>Report</strong> - Union’s Commitment to Andhra Pradesh<br />
Government of India should provide the<br />
Viability Gap Funding generously, so that<br />
the project can be executed.<br />
(v) An integrated steel plant in YSR<br />
District<br />
Government of India Commitment:<br />
Section 93 – Schedule 13 –<br />
Infrastructure item 3.<br />
“3. SAIL shall, within six months from the<br />
appointed day, examine the feasibility of<br />
establishing an integrated Steel Plant in<br />
YSR District of the Successor State of<br />
Andhra Pradesh;”<br />
As per the Thirteenth Schedule of the Andhra<br />
Pradesh Reorganisation Act, 2014, Steel<br />
Authority of India Limited (SAIL) 14 examined<br />
the feasibility of establishing an Integrated<br />
Steel Plant in YSR District of Andhra Pradesh.<br />
As per the feasibility report, setting up of Steel<br />
Plant was found prima facie not financially<br />
viable.<br />
Recently, the Government of Andhra Pradesh<br />
announced its decision to establish the Steel<br />
Plant as a State enterprise.<br />
12<br />
Flagship Scheme Details of MoPNG, (Details upto and including 9th April 2018 Ministry of Petroleum and Natural Gas, http://pibarchive.nic.in/<br />
4YearsOfNDA/Comprehensive-Materials/PNG.pdf<br />
13<br />
HPCL and GAIL requested State Government to consider providing VGF in the form of interest free loan of Rs. 1,438 crores per year to be<br />
provided for a period of 15 days beginning from Project Zero date. The interest free loan of Rs.1,438 crores per annum will be repaid by<br />
GAIUHPCL JV Company commencing from the 16th year onwards and ending in the 30th year after Project Zero date, free of any interest. In the<br />
meeting taken by the Hon’ble Chief Minister on 13.06.2017, GAIL and HPCL authorities were requested to provide the quantum of tax likely<br />
to be accrued to the State from the project under GST regime, to have further discussions. (Source: aplegislature.org/...on...<strong>AP</strong>...pdf/b706a359-<br />
1eac-46eaa73f-6dfd35a6dfd7 (Downloaded on 29 05 2018)<br />
14<br />
A Task Force comprising of representatives from the Central Government, State Government and Central Public Sector Enterprises under the<br />
Ministry of Steel was set up on 19.10.2016 to consider the feasibility issues and prepare a roadmap for setting up of steel plants.It has held<br />
series of meetings since then which were attended by the representatives of the State Governments of Andhra Pradesh as well. The last meeting<br />
of the Task Force, being sixth in the series of meetings, was held on 12.06.2018. (PIB 14-June-2018).<br />
- 77 -