Crossrail Western <strong>Tunnels</strong> and Bond Street and<br />

Tottenham Court Road Stations, London<br />

United Kingdom<br />

General Data:<br />

Project: Crossrail Western <strong>Tunnels</strong> and<br />

Bond Street and<br />

Tottenham Court Road Stations,<br />

single-track railway<br />

Client: Crossrail Limited, London, UK<br />

Contractor: <strong>Wayss</strong> & <strong>Freytag</strong> <strong>Ingenieurbau</strong> <strong>AG</strong><br />

in a joint venture<br />

Construction period: February 2011 to July 2015<br />

Construction costs: € 505 million<br />

Technical Data:<br />

Scope of work:<br />

Contract C300: Construction of 2 parallel, singletrack<br />

railway tunnels, length: 5.9 km<br />

each, internal diameter: 6.20 m;<br />

6 cross-passages; construction of<br />

Fisher Street Shaft and Crossover<br />

Contract C410: Construction of Bond Street and<br />

Tottenham Court Stations<br />

Construction method: Construction of the tunnels using 2<br />

EPB shields, shield diameter: 7.10 m;<br />

construction of stations using the<br />

sprayed concrete lining (SCL)<br />

method; construction of Fisher Street<br />

Shaft and Crossover using NATM<br />

techniques with a sprayed concrete<br />

inner lining<br />

Geology: London Clay<br />