Sluiskil Canal Crossing<br />
The Netherlands<br />
General Data:<br />
Project: Sluiskil Canal Crossing,<br />
twin-bore road tunnel under the Ghent-Terneuzen Canal<br />
Client: Province of Zeeland [Provincie Zeeland], represented by BV Kanaal-kruising Sluiskil<br />
Contractor: <strong>Wayss</strong> & <strong>Freytag</strong> <strong>Ingenieurbau</strong> <strong>AG</strong><br />
in a joint venture<br />
Construction period: October 2010 to August 2015<br />
Construction costs: € 208 million<br />
Technical Data:<br />
Scope of work: 2 parallel tunnel tubes, length: 1.15 km each, internal diameter: 10.10 m;<br />
4 cross-passages;<br />
2 ramp structures serving as start and/or target shafts;<br />
2 intersections - East and West - consisting of bridge structures with 2 roundabouts each<br />
Construction method: TBM tunnelling using a Hydroshield (slurry shield),<br />
shield diameter: 11.32 m,<br />
reinforced concrete segmental lining, wall thickness: 45 cm<br />
Geology: Sand, silt, Boom Clay, sand containing glauconite<br />
Ems-Dollard Crossing<br />
The Netherlands<br />
General Data:<br />
Project: Ems-Dollard Crossing between<br />
Germany and the Netherlands,<br />
tunnel for a gas pipeline<br />
Client: Nederlandse Gasunie<br />
Contractor: <strong>Wayss</strong> & <strong>Freytag</strong> <strong>Ingenieurbau</strong> <strong>AG</strong><br />
in a joint venture<br />
Construction period: June 2008 to September 2010<br />
Construction costs: € 47 million<br />
Technical Data:<br />
Scope of work: Tunnel for a gas pipeline,<br />
length: approx. 4,050 m,<br />
internal diameter: 3.0 m;<br />
start and target shaft;<br />
installation of the gas pipeline in the<br />
tunnel using the floating method and<br />
subsequent backfill grouting of the<br />
tunnel;<br />
extensive soil investigation<br />
Construction method: TBM tunnelling using a Hydroshield<br />
(slurry shield),<br />
shield diameter: 3.6 m;<br />
steel fibre reinforced segmental lining,<br />
wall thickness 25 cm<br />
Geology: Potklei (local type of clay), sands, clays<br />
34|35