New Central Services Tunnel for Brunsbüttel Lock<br />

Germany<br />

General Data:<br />

Project: New central services tunnel for Brunsbüttel lock, tunnel for service lines<br />

Client: Wasser- und Schifffahrtsamt Brunsbüttel [Water and Shipping Authority]<br />

Contractor: <strong>Wayss</strong> & <strong>Freytag</strong> <strong>Ingenieurbau</strong> <strong>AG</strong><br />

Construction period: March 2009 to September 2011<br />

Construction costs: € 22 million<br />

Technical Data:<br />

Scope of work: Construction of a services tunnel (called “Mitteldüker”) under the existing double<br />

locks at the western end of the Kiel Canal without disrupting lock operations,<br />

length: approx. 450 m, clear internal diameter: 2.20 m, tunnel invert approx. 35 m<br />

below ground level<br />

Construction method: Pipe jacking using an AVN 2000 machine,<br />

construction of shafts using the diaphragm wall method<br />

Geology: Gravelly sand with stones<br />

New Coal-Fired Power Plant in Wilhelmshaven,<br />

Cooling Water Pipelines, Lot C121, Germany<br />

General Data:<br />

Project: New coal-fired power plant in Wilhelmshaven,<br />

cooling water pipelines, Lot C121<br />

Client: GDF SUEZ Energie Deutschland <strong>AG</strong><br />

Contractor: <strong>Wayss</strong> & <strong>Freytag</strong> <strong>Ingenieurbau</strong> <strong>AG</strong><br />

in a joint venture<br />

Construction period: December 2009 - August 2011<br />

Construction costs: € 36 million<br />

Technical Data:<br />

Scope of work: 4 cooling water pipelines DN 3400 with a length of 300 m each;<br />

1 fish return pipeline DN 1200 with a length of 300 m;<br />

start shaft: 30 m x 25 m x 15 m, diaphragm walls with anchored underwater concrete slab;<br />

target shaft: 45 m x 11 m x 15 m, steel girder shoring with underwater concrete slab and pre-installed lean<br />

concrete block;<br />

dyke crossing structure: 5 circular cells of secant bored piles (internal diameter approx. 7 m), a tunnel drive<br />

through each circular cell<br />

Construction method: Pipe jacking using 2 slurry-supported tunnel boring machines, external diameter: 4.1 m<br />

Jacking pipes:<br />

Composite pipes DN 3400, consisting of a reinforced concrete pipe with an integrated HDPE pipe liner<br />

Geology: Silty sand with bands of clay<br />

10|11