CONTINUATION SHEET<br />
Name of Offeror or Contractor:<br />
C.2.4 Initial Support Package (ISP)<br />
Reference No. of Document Being Continued Page 78 of 170<br />
PIIN/SIIN W56HZV-12-R-0445<br />
MOD/AMD<br />
The contractor shall provide an ISP for each production BEB. The ISP shall consist of all service parts/items, with the exception of<br />
petroleum, oils and lubricants, required to meet service intervals during the first two years of service. The contractor shall mark<br />
each item/package with the nomenclature and part number. The contractor shall over-pack the ISP, to include the ISP list, with each<br />
BEB.<br />
C.2.4.1 ISP List<br />
The contractor shall provide an ISP list detailing all of the items to be included in the ISP. A complete ISP list shall include each<br />
item identified by nomenclature, part number and NSN (if assigned) (CDRL A003).<br />
C.2.5 Component of End Items (COEI)<br />
COEI are components that are part of the end item but must be removed and separately packaged for military transportation. The<br />
contractor shall over-pack the COEI with each BEB.<br />
C.2.6 Modifications for BEB Interface<br />
If any modifications are required for the CBT, PLST, IBC, or BAP to interface with the BEB, the contractor shall provide an installation<br />
modification kit and installation instruction over-packed with each BEB<br />
C.3 GOVERNMENT FURNISHED PROPERTY (GFP)<br />
The Government will provide GFP in accordance with Attachment 0003. The contractor shall manage the GFP in accordance with FAR 52.245-<br />
1.<br />
C.3.1 Contractor Requirements for Operating GFE<br />
The contractor shall have Operators/Maintainers who have an appropriate commercial drivers license to operate a CBT with and without the<br />
PLST.<br />
C.3.2 GFE Familiarization Training<br />
The contractor shall attend Government provided familiarization training at the contractors facility upon delivery of GFE. The<br />
Government will provide basic familiarization training to facilitate contractor operation of the GFE. Familiarization training will not<br />
exceed 40 hours. The contractor shall provide a list of attendees (not to exceed 12) to the Government at the Start of Work Meeting<br />
(SOWM).<br />
C.3.3 Preventive Maintenance for GFP<br />
The contractor shall conduct Preventive Maintenance Checks and Services (PMCS) outlined in the appropriate operator manuals.<br />
C.4 PROGRAM MANAGEMENT<br />
C.4.1 Participation/Logistics<br />
The contractor shall participate in the meetings and reviews required in this statement of work with Government attendance. The<br />
Government will determine when meetings shall be held by electronic means (via tele-conferences, email, etc). Physical meetings shall<br />
be synchronized to minimize personnel resources and travel expenses.<br />
C.4.2 Integrated Product Team (IPT)<br />
An Integrated Product Team (IPT) shall be established to serve as the primary management tool and key method of communication for this<br />
contract. As part of the SOWM, the Government and contractor will form IPTs. The Government IPT will be detailed in Attachment 0004.<br />
IPTs and membership shall be assigned in the areas of contract and program management, engineering, Integrated Logistics Support (ILS),<br />
publications, packaging, training, quality assurance, safety, human factors/MANPRINT, test progress and production status. The<br />
contractor shall be prepared to address all schedule, performance, supportability and risk issues during IPT meetings.<br />
C.4.3 Project Schedule<br />
DRAFT<br />
The contractor shall deliver a project schedule for the BEB Production phase. The project schedule shall include all milestones, system<br />
design and integration events, design meetings, Program Management Reviews, CDRL deliverable dates, test, modification, and logistics<br />
tasks required to complete the program, schedule, performance, and supportability requirements. The contractor shall maintain the