Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
mild climate, annual solar gains tend to<br />
be lower than other parts of the UK, so<br />
high levels of insulation and large are<strong>as</strong> of<br />
glazing were incorporated into the design to<br />
compensate for this and to enhance natural<br />
daylight levels,’ says Williamson.<br />
Construction<br />
The building uses a hybrid approach to<br />
construction. Its structural core of internal<br />
partition walls is constructed from concrete<br />
blocks mounted on a c<strong>as</strong>t in-situ concrete<br />
ground floor slab, while the external walls<br />
are prefabricated timber frame and c<strong>as</strong>sette<br />
construction. The wood-faced c<strong>as</strong>settes<br />
incorporate recycled newspaper insulation.<br />
The first floor is constructed from hollowcore<br />
concrete slabs. This solution adds<br />
thermal m<strong>as</strong>s to the interior while allowing<br />
a highly insulated facade system to be used.<br />
‘We took a fabric-first approach to the low<br />
energy design because the fabric will be<br />
in place for at le<strong>as</strong>t 60 years,’ Williamson<br />
explains.<br />
An <strong>as</strong>ymmetrical pitched roof caps the<br />
building. Its south-facing, slate-clad <strong>as</strong>pect<br />
is pitched at 35 degrees to<br />
ensure its 7 kWp covering<br />
of photovoltaic panels<br />
performs effectively. The<br />
north-facing slope is much<br />
gentler to enable the living<br />
sedum roof to flourish. A<br />
green roof also blankets the<br />
building’s large entrance<br />
lobby to help enhance the<br />
site ecology.<br />
Fabric airtightness<br />
is fundamental to the<br />
building’s low energy<br />
performance. An interior<br />
breathable membrane is used to seal<br />
the facades. ‘The biggest challenge w<strong>as</strong><br />
detailing around the windows, floor plate<br />
and wall junctions and where M&E services<br />
enter the building,’ says Williamson. ‘The<br />
junctions had to be airtight without creating<br />
a thermal bridge and the designs had to be<br />
approved by the P<strong>as</strong>sivhaus Institut. ‘It w<strong>as</strong><br />
important the timber c<strong>as</strong>sette manufacturer<br />
and structural engineer bought into the<br />
detailing because they have to stand by their<br />
warranty,’ explains Williamson.<br />
C Sneade, a family-owned local contractor,<br />
w<strong>as</strong> selected to construct the low-energy<br />
building. The contractor worked alongside<br />
the designers to ensure the building w<strong>as</strong><br />
airtight. Construction joints were pressuretested<br />
before being covered with internal<br />
linings. This enabled any reworking to be<br />
done with the minimum of disturbance.<br />
However, it also required a change to the<br />
conventional construction programme to<br />
ensure the building’s fabric w<strong>as</strong> complete<br />
and windows installed earlier than usual in<br />
the programme, which could be an issue<br />
on larger schemes if the works cannot be<br />
ph<strong>as</strong>ed accordingly.<br />
JPW challenged the contractor to make<br />
the building more airtight than their<br />
German counterparts were currently<br />
achieving. The applied psychology clearly<br />
worked; when the scheme w<strong>as</strong> fully<br />
pressure tested it registered 0.37cu m/h/<br />
sq m at 50 Pa, which is one of the lowest air<br />
leakage rates ever achieved in the UK.<br />
Ventilation<br />
With so little air infiltration, the ventilation<br />
design is critical. The designers considered<br />
natural ventilation for the scheme, but<br />
at £500 per actuator per window it w<strong>as</strong><br />
expensive and potentially ineffective on<br />
days when there w<strong>as</strong> no wind. Instead JPW<br />
Associates opted for mechanical ventilation<br />
with heat recovery (MVHR). The problem<br />
with this option w<strong>as</strong><br />
that the P<strong>as</strong>sivhaus<br />
fresh air requirement<br />
w<strong>as</strong> only eight litres per<br />
second, but Part F of the<br />
Building Regulations<br />
have a greater fresh air<br />
requirement of 10 l/s<br />
per person. Williamson<br />
says the designers<br />
compromised by<br />
designing a system with<br />
step control capable of<br />
delivering fresh air at<br />
quantities up to 10 l/s.<br />
Five P<strong>as</strong>sivhaus-approved Drexel and<br />
Weiss ventilation units have been installed,<br />
one for each computer room, with the<br />
remaining two units serving the offices<br />
and public are<strong>as</strong>. The units operate on<br />
three speeds: high, medium and low, with<br />
medium being the default for public are<strong>as</strong>.<br />
In summer the MVHR system will supply<br />
fresh air during the day. At night the system<br />
will run to purge heat from the heavy<br />
construction elements if the outside air is<br />
greater than 4C cooler than the internal<br />
temperature. To save fan energy and prevent<br />
any heat transfer, the ventilation units’ heat<br />
exchangers are removed in summer to<br />
enable them to run at 100% byp<strong>as</strong>s.<br />
Williamson did consider using<br />
mechanical cooling for the scheme <strong>as</strong><br />
an alternative to running power-hungry<br />
It proved difficult<br />
to satisfy both the<br />
BREEAM and<br />
P<strong>as</strong>sivhaus Institut<br />
rating systems.<br />
Creating two sets<br />
of data w<strong>as</strong> time<br />
consuming and<br />
added to design costs<br />
OffiCe C<strong>as</strong>e study cibse AwArd winner<br />
KeyfaCts<br />
POwys cOuncil’s<br />
cAnOlfAn hyddgen in<br />
mAchynlleth, wAles<br />
Structure and fabric:<br />
A central m<strong>as</strong>onry core from<br />
reclaimed and recycled m<strong>as</strong>onry<br />
in conjunction with in situ<br />
ground-floor slab (60% ground<br />
granulated bl<strong>as</strong>t furnace slag),<br />
with an external solid timber<br />
frame and I-beam C<strong>as</strong>sette roof;<br />
7kw PV array.<br />
airtightneSS: n50 = 0.249-1<br />
@ 50Pa (P<strong>as</strong>sivhaus Institute<br />
requirement is 0.6); Q50=0.37cu<br />
m/(h.sq m)@50 Pa (UK<br />
me<strong>as</strong>urement).<br />
venilation/heat recovery:<br />
Five Drexel & Weiss Aero<br />
business units operate across<br />
five different zones. Three<br />
ventilation levels are varied<br />
automatically according to PIR<br />
and timer controls.<br />
Space heating: 9-24 kW g<strong>as</strong><br />
boiler; point-of-use electric water<br />
heaters in toilets, kitchen and<br />
cleaners cupboards.<br />
lighting: PIR and daylight<br />
balancing is used throughout the<br />
building which complements the<br />
hybrid decentralised/centralised<br />
building ventilation strategy:<br />
rooms and equipment only<br />
power up when they are in use.<br />
energy management<br />
SyStem: System control board<br />
is linked to County Hall, allowing<br />
remote monitoring and enabling<br />
local key holders and caretakers<br />
to manage the building under<br />
instruction from centralised<br />
energy managers.<br />
monitoring: JPW h<strong>as</strong> applied<br />
for funding to expand monitoring<br />
and analysis of the building and<br />
hopes to use <strong>CIBSE</strong> TM22 and<br />
BUS questionnaires to gather<br />
more information and compare<br />
actual efficiencies with building<br />
physics methodologies and<br />
prediction tools. They will do this<br />
using: sub-meters to monitor<br />
individually tenanted office spaces;<br />
focused mobile monitoring of<br />
selected workspaces for actual<br />
and perceived comfort levels<br />
b<strong>as</strong>ed on CO2, relative humidity,<br />
temperature and daylight levels;<br />
and the actual use of operational<br />
energy in IT and similar<br />
equipment.<br />
www.cibsejournal.com April 2011 <strong>CIBSE</strong> <strong>Journal</strong> 37