Coquitlam Dam Seismic Upgrade Project ... - BC Hydro
Coquitlam Dam Seismic Upgrade Project ... - BC Hydro
Coquitlam Dam Seismic Upgrade Project ... - BC Hydro
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Note: To ensure the protection of aquatic life and their habitats, <strong>BC</strong> <strong>Hydro</strong> and its<br />
contractors will ensure that water exiting the construction areas and entering a<br />
drainage course will meet the following criteria:<br />
Total Suspended Solids: 1) 25 mg/l above background during dry weather<br />
2) 75 mg/l above background during design storm event<br />
There will be no sediment laden water permitted to enter the reservoir.<br />
Efforts will be made to control silt-laden runoff from the working and stockpile areas. This will<br />
involve utilizing a combination of several techniques on a site-specific basis as described below:<br />
• Installation of upslope drainage interception to remove clean uncontaminated water and<br />
reduce amount of water flowing through the site.<br />
• Minimize the exposed area for excavation at any one time. Once excavation is completed<br />
within an area it will be immediately restored to finish grade, layered with a compost<br />
medium and re-vegetated. Additional erosion control measures such as wattle fences,<br />
fascines and live pole drains may also be required in some areas.<br />
• Installation of cross-slope swales to enhance drainage and to prevent erosion of excavated<br />
materials.<br />
• Installation of silt fence material on the downslope side between working areas or stockpile<br />
areas and any drainages or wetlands; these will be set up prior to the initiation of any<br />
excavation work; the geotextile fence fabric shall be Terrafix 370 RF, AMOCO 2125 or an<br />
approved equivalent.<br />
• Isolation of any identified sensitive sites with fencing, ribbon or rope to exclude accidental<br />
intrusion.<br />
• Filter cloth and clean gravel will be readily available on-site should they be required; these<br />
materials provide a reasonably effective, on the spot filtration device in field situations and<br />
may be placed in any small ditches etc. to filter water laden with silt or sediments.<br />
• Ditches and culverts will be used to maintain adequate drainage over the newly excavated<br />
site.<br />
• Natural drainage patterns will be retained wherever possible.<br />
• Soil excavation stockpiles will either be completely contained by berms and silt fences or<br />
covered with polyethylene to prevent erosion.<br />
• Settling ponds will be constructed to clarify turbid water prior to release from the site.<br />
Construction of settling ponds will be completed in accordance with the ‘Land Development<br />
Guidelines for the Protection of Aquatic Habitat’.<br />
• Should site discharge water not meet the legislated criteria, the Contractor will be requested<br />
to implement other techniques to ensure the water entering watercourses meets authorized<br />
levels. These methods can include, but will not be limited to, trucking of water, dispersion of<br />
<strong>Coquitlam</strong> <strong>Dam</strong> <strong>Seismic</strong> Rehabilitation Page 17<br />
Environmental Management Plan – Version 4<br />
June 15, 2004