Doc No. SALT<strong>1700AS0001</strong> Issue A<br />

<strong>TCS</strong> <strong>Spec</strong>ification<br />

The emergency power source shall has the following features:<br />

• It will become active within 30s of a general power failure and will remain on until<br />

manually turned off<br />

• The quality of power (voltage, frequency drift, harmonics) will be no worse than the<br />

normal electrical supply<br />

• At least the following error conditions will also be reported to the <strong>TCS</strong>: low fuel, low oil<br />

pressure, generator fault, low voltage, over-current, system overheating, power status<br />

(normal, emergency, off).<br />

If the generator fails to start after a power failure an operator warning shall be generated so<br />

that critical software processes can be shut down.<br />

5.5.12 Data security<br />

a. The <strong>TCS</strong> shall allow various users to log in with different levels of security. The following level<br />

of access are required, each with their own particular restrictions:<br />

• SA<br />

• SO<br />

• Maintainer<br />

• Administrator<br />

• PI<br />

• Co-Investigator<br />

• Partner<br />

• Guest<br />

b. A firewall shall protect the SALT network from unauthorised access outside the site.<br />

5.5.13 Future growth<br />

The following potential growth areas shall be borne in mind during the design process and<br />

accommodated where this does not have an impact on the achievement of the immediate<br />

performance, schedule and cost requirements.<br />

5.5.13.1 PHASING<br />

The primary mirror array of SALT may be required to be phased in future, to make use of the<br />

advantages of Adaptive Optics (AO).<br />

5.5.13.2 IMPROVED OPTICAL PERFORMANCE<br />

The optical performance of SALT may be improved by using the latest technology mirror<br />

coatings.<br />

5.5.13.3 IR PFIS<br />

A near IR channel may be added to the PFIS.<br />

5.5.13.4 REMOTE OBSERVING<br />

The whole or parts of the SALT control room may be required to be duplicated at the SAAO in<br />

Cape Town, to allow remote operating of SALT.<br />

5.5.13.5 ADDITIONAL INSTRUMENTS<br />

<strong>Spec</strong>ific provisions shall be made in the <strong>TCS</strong> architecture, network sizing and MMI design to<br />

facilitate the addition of more science instruments during SALT’s life-time.<br />