GUIDELINES ON TWINNING INSTRUMENT FOR PROGRAMME ADMINISTRATION AGENCY<br />

• A project fiche for the Tw<strong>in</strong>n<strong>in</strong>g project should be provided with<strong>in</strong> 40 calendar days after the<br />

signature <strong>of</strong> the contract. Subsequent drafts will be prepared upon the guidance <strong>of</strong> the<br />

Commission services.<br />

• A F<strong>in</strong>al Report: this will provide a detailed summary <strong>of</strong> activities implemented, problems<br />

encountered and solutions adopted, a detailed description <strong>of</strong> results achieved. The experts are<br />

<strong>in</strong>vited to <strong>in</strong>clude <strong>in</strong> this report, as far as possible, proposals for activities to be developed <strong>in</strong> the<br />

sector, as a complement to the Tw<strong>in</strong>n<strong>in</strong>g project<br />

5.2. Language<br />

The <strong>in</strong>ception and f<strong>in</strong>al reports must be submitted <strong>in</strong> English. The drafts <strong>of</strong> the Tw<strong>in</strong>n<strong>in</strong>g fiche must<br />

be <strong>in</strong> English and translated <strong>in</strong>to Armenian with<strong>in</strong> 5 work<strong>in</strong>g days maximum.<br />

5.3. Number <strong>of</strong> report(s) copies<br />

The experts will give a set <strong>of</strong> 3 paper copies and 1 electronic version <strong>of</strong> their reports to both the<br />

<strong>PAO</strong>/SATTO <strong>in</strong> Yerevan and the European Commission Delegation to Armenia as the Contract<strong>in</strong>g<br />

Authority.<br />

6. ADMINISTRATIVE INFORMATION<br />

The Contractor must make available an appropriate logistical support for the experts, <strong>in</strong>clud<strong>in</strong>g<br />

their travel, visa and accommodation arrangements for each assignment.<br />

Eligibility: all nationalities are eligible.<br />

Equipment: No equipment is to be purchased on behalf <strong>of</strong> the Contract<strong>in</strong>g Authority/beneficiary<br />

country with<strong>in</strong> the context <strong>of</strong> this contract.<br />

Budget: The maximum budget available is 80,000 EUR.<br />

Secretarial/<strong>of</strong>fice-related costs which may <strong>in</strong>clude communications (fax, telecommunications, mail,<br />

courier etc.), report production and secretarial services both <strong>in</strong> the Contractor’s Headquarters<br />

and/or <strong>in</strong>dividual expert’s home <strong>of</strong>fice and for experts <strong>in</strong> the beneficiary country are considered to<br />

be <strong>in</strong>cluded with<strong>in</strong> the fee rates <strong>of</strong> the experts. No costs <strong>of</strong> this nature may be charged <strong>in</strong> addition.<br />

The fee rate and per diem amount which should be used are those <strong>in</strong> force on the date <strong>of</strong> the<br />

signature <strong>of</strong> the Request for services. No price revision is foreseen dur<strong>in</strong>g the duration <strong>of</strong> this<br />

contract.<br />

Reimbursable costs: Appropriate budgetary allocations should be foreseen under "reimbursable<br />

costs" at least for:<br />

- Per diems<br />

- International Travel costs<br />

- Interpretation/Translation<br />

7. FOLLOW UP AND EVALUATION<br />

The project will have to be developed along the standard European Commission rules and<br />

procedures.<br />

43

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!