MSR 2002-2 - Public Service Commission of West Virginia
MSR 2002-2 - Public Service Commission of West Virginia
MSR 2002-2 - Public Service Commission of West Virginia
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>Public</strong> <strong>Service</strong> <strong>Commission</strong> — Management Summary Report<br />
The <strong>Commission</strong> issued two orders on April 7, 2006 approving stipulations filed in the<br />
respective cases. The <strong>Commission</strong> approved the asset swap in the first four cases and approved<br />
the certificate and securitization financing in the remaining two.<br />
Case Nos. 05-0402-E-CN and 05-0750-E-PC were reopened in October for consideration<br />
<strong>of</strong> increased project costs.<br />
Electric Generation Projects - During 2006, the <strong>Commission</strong> granted, with extensive<br />
conditions, a siting certificate to locate a 186 MW windmill facility in Greenbrier County, on<br />
a 100,000-acre tract owned by Mead<strong>West</strong>vaco, which had previously been timbered and mined.<br />
More than 100 1.5 MW wind turbines were approved, and the total cost was projected to be<br />
$300 million. The project will create more than 200 temporary construction jobs and 15-20<br />
permanent jobs with a $35,000 average annual salary. Further, it will result in $400,000 yearly<br />
in tax revenue to Greenbrier County for 20 years and $200,000 yearly in tax revenue to the<br />
state, as well as contribute to a growth in tourism. There was extensive public participation in<br />
this case, and the <strong>Commission</strong> conducted two public comment hearings in Lewisburg and six<br />
days <strong>of</strong> evidentiary hearings in Charleston. At year’s end, the <strong>Commission</strong> was deliberating<br />
petitions to reconsider that decision.<br />
The <strong>Commission</strong> held a hearing in December 2006 on another windmill project proposed<br />
for construction in Pendleton County. If a siting certificate is granted, the facility would be<br />
comprised <strong>of</strong> 50 wind turbines, each with a rated capacity <strong>of</strong> between 1,500 and 3,000 kilowatts,<br />
and certain ancillary facilities, and an approximate 17.25 mile, 138 kV overhead transmission<br />
line to interconnect the facility to the Allegheny Power System (APS) electric transmission<br />
system. The total output <strong>of</strong> the Facility would be up to 125 megawatts. The general location <strong>of</strong><br />
the Facility is on the Jack Mountain ridge top approximately ten miles outside <strong>of</strong> Franklin in<br />
Pendleton County, <strong>West</strong> <strong>Virginia</strong>. The <strong>Commission</strong> anticipates issuing its final decision on<br />
the application in March 2007. This application is docketed as Case No. 05-1740-CS-CN and<br />
the applicant is Liberty Gap Wind Force, LLC .<br />
The <strong>Commission</strong> is currently considering Appalachian Power Company’s application for a<br />
certificate <strong>of</strong> convenience and necessity to construct a 600 MW Integrated Gasification<br />
Combined Cycle electric generating unit in Mason County in Case No. 06-0033-E-CN. A<br />
hearing in this case scheduled for March 2007.<br />
By a <strong>Commission</strong> Order entered June 26, 2006 the <strong>Commission</strong> granted the applications<br />
<strong>of</strong> Longview Power, LLC for a Siting Certificate to authorize the construction and operation<br />
<strong>of</strong> a 600 MW coal-fired electric power plant Wholesale Electric Generating Facility and for<br />
a Certificate <strong>of</strong> <strong>Public</strong> Convenience and Necessity for the construction and installation <strong>of</strong> a<br />
Page 13