Native Plant Synoptic Garden<br />
89<br />
____________________________________________________________________________________________________________<br />
of these projects are $4, 037,000 <strong>and</strong> $4,818,000 respectively, <strong>and</strong> again these numbers are in<br />
terms of 2003 dollars (ABGC, 2004).<br />
In a meeting with the Grounds Maintenance Supervisor, David Zuckerman, we obtained<br />
the 2003/2004 Washington Park Arboretum Budget Plan which is included as Appendix C. Mr.<br />
Zuckerman explained that the budget represents the entire Washington Park Arboretum’s<br />
maintenance costs, <strong>and</strong> that operating costs are not itemized for different areas within the<br />
arboretum. As a result, any added personnel <strong>and</strong> equipment costs would be shared as part of the<br />
budget for the entire rejuvenation project. The annual grounds maintenance budget for 2003 <strong>and</strong><br />
2004 is just over $230,000 according to the Washington Park Arboretum Budget Plan. Projected<br />
annual maintenance <strong>and</strong> operating costs for the Native Plant Synoptic garden <strong>and</strong> its surrounding<br />
gardens (around Graham Visitors Center) is $461,000 in 2003 dollars (ABGC, 2004). This is<br />
more than double the current operating budget projected for the upcoming year. However, it<br />
should be noted that much of that budget will be devoted to maintenance <strong>and</strong> operation of<br />
intensive plant, tree, <strong>and</strong> shrub beds around the Graham Visitors Center; this area accounts for<br />
$319,000 of the $461,000 <strong>and</strong> therefore does not fairly represent costs incurred directly from the<br />
Native Plant Synoptic Garden. Also, the projected $461,000 is only a portion of the entire<br />
maintenance <strong>and</strong> operating budget that is projected for implementation of the entire Washington<br />
Park Arboretum Master Plan (ABGC, 2004).<br />
Maintenance amounts include wages <strong>and</strong> benefits of all maintenance employees. The<br />
estimated cost of maintenance for these three portions is double the total 2003/2004 Washington<br />
Park Arboretum annual budget. The projected significant raise in annual maintenance costs are<br />
due to the added gardens that require more intense maintenance than the current gardens do, <strong>and</strong><br />
the assumption that there will be a significant addition of full time staff to carry out the<br />
maintenance. There were around twenty full time employees maintaining the Arboretum in early<br />
2004; however, the Master Plan calls for an additional sixty full time employees to implement<br />
<strong>and</strong> maintain Washington Park Arboretum after implementation of the Master Plan (ABGC,<br />
2004).<br />
Money from endowments is the major resource from which future funding for these<br />
projects will be generated. The Arboretum currently relies on interest from endowments, which<br />
compounds at 5% <strong>and</strong> is used to pay the staff <strong>and</strong> cover operating costs (AGBC, 2004). Other<br />
major funding for the rejuvenation project will come from contributions made from the public to<br />
the Arboretum Foundation. The Foundation’s primary goal during implementation of the Master<br />
Plan is to raise funds. These donations/funds could come from private investors, the<br />
city/county/state legislature, or directly from Washington Park Arboretum users.