Events Forecast in 2005<br />
— May 2005 – a meeting is planned by the Ústecko Region autonomous governing body to discuss territorial<br />
ecological limits (as part of the procedure to approve the region’s land-use plan and energy policy)<br />
— update of the long-term purchase agreement with ČEZ<br />
— ČEZ decision on the scope of reconstruction of CHP plants, including a schedule for the shutdown<br />
of the facilities to be reconstructed and renovated<br />
— implementation of further modules of the new SAP information system<br />
Doly Bílina<br />
— April to May 2005 – extensive reconstruction of the conveyor belt facilities of the fifth section, with<br />
a reduction in the level and the relaying of the belt conveyors<br />
— April to June 2005 – partial general overhaul and reconstruction of the electrics and electronics of the spreader<br />
ZPD 8000/Z98<br />
— July 2005 – completion of the general overhaul of the K 2000/K101 large-scale excavator<br />
— August 2005 – launch of the general overhaul of the KU 800/K99 large-scale excavator<br />
— December 2005 – completion of a significant ecological project: transfer of water discharge and treatment from<br />
the Ledvice pumping station to the main pumping station (termination of the discharge of water to Ledvice<br />
Stream)<br />
Doly Nástup Tušimice<br />
— completion of the assembly of the second ‘heavy’ SchRs 1320 excavator (August 2005), transfer to the point<br />
of use; launch of trial and then permanent operation in the final quarter of 2005<br />
— completion of the modernization of the mine water treatment plant in Březno<br />
— first stage of modernization and general overhaul of ÚDUT II<br />
— completion of the optimization of the organizational structure – the merger of operating sections<br />
at the overburden operation and quarry operation (abandonment of the Málkov and Zásada complex)<br />
— reduction in the excavation of overburden by reducing the shift system at the first overburden bench by one<br />
shift as of 1 July 2005 in accordance with the expected decline in coal mining due to the planned general<br />
overhaul of ETU II between 2007 and 2010<br />
— the advance of the overburden and coal sections and spoil bank will reach the area of the deep coal seam<br />
(the ‘Kralupy Fault’ area) and there is a risk that the overburden, coal, and spoil banks will slide even if<br />
adopted measures and subsequently adopted extraordinary measures are respected and implemented