02.03.2013 Views

Management of the Holyrood building project (PDF ... - Audit Scotland

Management of the Holyrood building project (PDF ... - Audit Scotland

Management of the Holyrood building project (PDF ... - Audit Scotland

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

40<br />

3.8 Construction management is<br />

quite different to a traditional <strong>building</strong><br />

contract. The main benefit is shorter<br />

timescales. Construction<br />

management compresses <strong>the</strong> overall<br />

design and construction programme<br />

by allowing procurement and<br />

construction to proceed before <strong>the</strong><br />

design <strong>of</strong> all packages is completed.<br />

It is intended for use when <strong>the</strong>re is a<br />

compelling value for money case for<br />

completing a <strong>building</strong> <strong>project</strong> at <strong>the</strong><br />

earliest possible date (eg, to benefit<br />

from forecast high rental incomes, or<br />

to achieve unmoveable opening dates).<br />

3.9 Under construction management<br />

contractors commence works before<br />

all design is completed. There are<br />

risks in this, for example in<br />

proceeding with <strong>the</strong> foundations and<br />

substructure <strong>of</strong> a <strong>building</strong> without a<br />

complete understanding <strong>of</strong> <strong>the</strong><br />

superstructure design. Because <strong>the</strong><br />

client contracts with <strong>the</strong> trade<br />

contractors directly <strong>the</strong>re is no main<br />

contractor to accept and manage<br />

risks from programming and<br />

coordination <strong>of</strong> contractors. The<br />

design team must envisage <strong>the</strong><br />

totality <strong>of</strong> <strong>the</strong> design, accommodate<br />

any uncertainty in later, dependent<br />

packages and progress long leadtime<br />

items (eg, lift packages) early in<br />

<strong>the</strong> procurement process. There<br />

needs to be experience, team spirit<br />

and cooperation to manage <strong>the</strong> risks.<br />

3.10 The advantage <strong>of</strong> construction<br />

management is that <strong>the</strong> design <strong>of</strong><br />

packages <strong>of</strong> work may be changed<br />

up to <strong>the</strong> point when <strong>the</strong> contract is<br />

awarded without necessarily<br />

incurring additional costs for those<br />

packages. Once packages are let,<br />

<strong>the</strong>ir content should be fixed.<br />

Unforeseen change after a contract<br />

is let is likely to incur delay and<br />

additional costs.<br />

3.11 The audit examination does not<br />

provide a detailed assessment <strong>of</strong> all<br />

<strong>the</strong> changes made during <strong>the</strong><br />

<strong>Holyrood</strong> <strong>project</strong>. That would be an<br />

enormous undertaking. The<br />

Corporate Body has estimated <strong>the</strong>re<br />

have been some 10,000 proposed<br />

change orders issued over <strong>the</strong><br />

course <strong>of</strong> <strong>the</strong> <strong>project</strong>. Many <strong>of</strong> <strong>the</strong>se<br />

changes could be small and some<br />

may have arisen before <strong>the</strong> Stage D<br />

approval. However <strong>the</strong> very<br />

significant impact <strong>of</strong> change in each<br />

contract at awarded is evident from a<br />

simple comparison <strong>of</strong> <strong>the</strong> cost <strong>of</strong> <strong>the</strong><br />

contract at tender/contract award<br />

stage and <strong>the</strong> current forecast<br />

outturn (Exhibit 20).<br />

The complexity <strong>of</strong> <strong>the</strong> <strong>Holyrood</strong><br />

<strong>project</strong> has involved major<br />

challenges in programming <strong>the</strong><br />

construction<br />

3.12 Before tenders for <strong>the</strong> main<br />

<strong>building</strong> work in <strong>the</strong> east <strong>of</strong> <strong>the</strong><br />

<strong>Holyrood</strong> site could be obtained, <strong>the</strong><br />

design team had to develop <strong>the</strong> June<br />

2000 Stage D design into detailed<br />

package designs to provide sufficient<br />

information for tendering. This was a<br />

very large task for <strong>the</strong> design team<br />

and <strong>the</strong> construction manager.<br />

• The Stage D design was not a<br />

fully developed and coordinated<br />

design. The client accepted this<br />

as an architectural Stage D,<br />

though some elements, for<br />

example <strong>the</strong> foyer ro<strong>of</strong>, were no<br />

more than concept design (Stage<br />

C). The client recognised <strong>the</strong><br />

structural and service design<br />

information was not equivalent to<br />

Stage D. Despite <strong>the</strong> complex<br />

structures and organically shaped<br />

<strong>building</strong>s, only comparatively<br />

small-scale drawings were<br />

provided at Stage D. Exhibit 21<br />

(overleaf) illustrates design<br />

development <strong>of</strong> <strong>the</strong> foyer ro<strong>of</strong><br />

since <strong>the</strong> Stage D design, and <strong>the</strong><br />

extent <strong>of</strong> <strong>the</strong> initial uncertainty.<br />

• Programme 3C which envisaged<br />

completion by December 2002<br />

was issued on 22 July 2000.<br />

There were very short timescales<br />

for subsequent design details to<br />

be provided. For example, <strong>the</strong><br />

target date for sending out <strong>the</strong><br />

tenders for <strong>the</strong> assembly <strong>building</strong><br />

superstructure package – <strong>the</strong><br />

largest and most costly package –<br />

was 11 August 2000. This was<br />

just seven weeks after <strong>the</strong> Stage<br />

D design was approved without a<br />

Stage D engineering design.<br />

3.13 In addition to <strong>the</strong> challenges <strong>of</strong><br />

<strong>the</strong> design programme particular<br />

difficulties arose because:<br />

• unforeseen structural and<br />

conservation matters affected<br />

Queensberry House. There were<br />

delays in securing agreement on<br />

<strong>the</strong> reconstruction that was<br />

required to take into account <strong>the</strong><br />

fact that Queensberry House was<br />

a listed <strong>building</strong> and securing <strong>the</strong><br />

required listed <strong>building</strong> consents<br />

• because <strong>of</strong> <strong>the</strong> complexity <strong>of</strong><br />

much <strong>of</strong> <strong>the</strong> work, <strong>the</strong><br />

interdependency <strong>of</strong> many<br />

elements and congestion on <strong>the</strong><br />

site, <strong>the</strong>re were unforeseen<br />

problems and delays. Exhibit 22<br />

(overleaf) illustrates a few examples<br />

<strong>of</strong> <strong>the</strong>se unforeseen difficulties.<br />

3.14 The construction manager’s<br />

responsibilities are detailed in its<br />

contract with <strong>the</strong> Corporate Body. Its<br />

responsibilities include:<br />

• liaison and consultation with all<br />

parties<br />

• coordinating <strong>the</strong> services <strong>of</strong> <strong>the</strong><br />

design team with <strong>the</strong> execution<br />

and completion <strong>of</strong> <strong>the</strong> <strong>project</strong> by<br />

<strong>the</strong> trade contractors<br />

• securing agreement to <strong>the</strong> cost<br />

plan by <strong>the</strong> client and <strong>the</strong> cost<br />

consultant as soon as practicable<br />

• ensuring that <strong>the</strong> <strong>project</strong> is executed<br />

and completed within <strong>the</strong> cost<br />

plan and construction period<br />

• programming at all levels <strong>of</strong><br />

construction

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!