02.03.2013 Views

Management of the Holyrood building project (PDF ... - Audit Scotland

Management of the Holyrood building project (PDF ... - Audit Scotland

Management of the Holyrood building project (PDF ... - Audit Scotland

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Exhibit 30<br />

<strong>Holyrood</strong> – estimated construction costs from 2000 to 2004<br />

£100 milllion<br />

4<br />

3<br />

2<br />

1<br />

0<br />

September 2000<br />

December 2000<br />

Source: <strong>Audit</strong> <strong>Scotland</strong><br />

Exhibit 31<br />

Design development <strong>of</strong> <strong>the</strong> foyer ro<strong>of</strong> and glazing package<br />

Source: <strong>Audit</strong> <strong>Scotland</strong><br />

March 2001<br />

June 2001<br />

September 2001<br />

December 2001<br />

March 2002<br />

June 2002<br />

September 2002<br />

December 2002<br />

Part 4. The reasons for increased costs 55<br />

March 2003<br />

June 2003<br />

September 2003<br />

December 2003<br />

March 2004<br />

Total costs<br />

Total <strong>project</strong> costs reported<br />

to Finance Committee<br />

Construction costs (shaded)<br />

Construction risk<br />

Increased construction<br />

costs over cost plan<br />

Construction inflation<br />

Construction cost plan<br />

Late in 1999 <strong>the</strong> foyer area was introduced as a comparatively late addition to <strong>the</strong> concept design <strong>of</strong> <strong>the</strong><br />

Parliament. It would provide necessary additional space for <strong>the</strong> client and remove <strong>the</strong> need for circulation between<br />

<strong>the</strong> MSP block and <strong>the</strong> assembly <strong>building</strong>s complex to go through Queensberry House as previously planned.<br />

The Stage D cost plan in November 2000 included £1.5 million for this part <strong>of</strong> <strong>the</strong> <strong>building</strong>. There was very little<br />

design information. The cost plan allowed a lump sum <strong>of</strong> £0.7 million (with no quantities or rates) plus £0.8 million<br />

for <strong>the</strong> glazed ro<strong>of</strong> costed at £500/m 2 .<br />

The work was procured using <strong>the</strong> two-stage process. At <strong>the</strong> first tender stage in June 2001 a price <strong>of</strong> some<br />

£2 million was obtained and accepted. As <strong>the</strong> requirements were clarified and design developed between <strong>the</strong><br />

contractor and <strong>the</strong> architect, estimated costs increased to £4.2 million, £4.9 million and <strong>the</strong>n in December 2001<br />

£6.2 million. This included £1.2 million for oak and steel finishes alone, almost <strong>the</strong> whole value <strong>of</strong> <strong>the</strong> original cost<br />

plan allowance.<br />

In December 2001 <strong>the</strong> Progress Group concluded <strong>the</strong>re was little scope to save costs as any redesign would<br />

significantly delay <strong>the</strong> overall programme and increase costs elsewhere. It accepted <strong>the</strong> developing design<br />

reluctantly and allowed development to continue.<br />

Exhibit 21 illustrates how <strong>the</strong> design <strong>of</strong> <strong>the</strong> area developed between 2000 and as it has now been constructed.<br />

The current estimated cost <strong>of</strong> <strong>the</strong> contract is some £7.4 million excluding risk. The extra costs appear to be <strong>the</strong><br />

result <strong>of</strong> <strong>the</strong> inability <strong>of</strong> <strong>the</strong> contractor to price <strong>the</strong> contract fully at tender with <strong>the</strong> limited design information<br />

available; <strong>the</strong> degree <strong>of</strong> design development on <strong>the</strong> package post tender; and extensions <strong>of</strong> time for delays due to<br />

o<strong>the</strong>r packages not completing on time and cranage access.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!