Management of the Holyrood building project (PDF ... - Audit Scotland
Management of the Holyrood building project (PDF ... - Audit Scotland
Management of the Holyrood building project (PDF ... - Audit Scotland
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
4.36 After construction started <strong>the</strong><br />
construction manager held regular<br />
design meetings, cost meetings and<br />
progress meetings for each package.<br />
However, <strong>the</strong> effectiveness <strong>of</strong><br />
management and control has almost<br />
certainly been compromised by <strong>the</strong><br />
strict requirement to adhere to<br />
programme targets that could be said<br />
to have been unachievable. Driving<br />
trade contractors to comply with<br />
unachievable programmes increases<br />
costs, in terms <strong>of</strong> prolongation costs<br />
and also in disruption costs.<br />
4.37 Eight <strong>of</strong> <strong>the</strong> 20 packages<br />
reviewed were awarded on <strong>the</strong> basis<br />
ei<strong>the</strong>r that <strong>the</strong> outstanding design<br />
would be completed within an<br />
agreed period after award or simply<br />
as quickly as possible. In <strong>the</strong>se<br />
cases, for coordination, <strong>the</strong><br />
construction manger ensured that a<br />
schedule was agreed that showed<br />
<strong>the</strong> latest dates that <strong>the</strong> trade<br />
contractor needed design information<br />
from <strong>the</strong> design team. Achievement<br />
<strong>of</strong> <strong>the</strong> design programme slipped<br />
from <strong>the</strong> agreed dates and this<br />
design slippage within individual<br />
packages contributed to <strong>the</strong> overall<br />
delay, as a delay on one package can<br />
affect o<strong>the</strong>r packages, and so on.<br />
4.38 Even where <strong>the</strong> performance <strong>of</strong><br />
trade contractors may not have been<br />
satisfactory, <strong>the</strong>re was in some<br />
cases little opportunity to attribute<br />
delays to <strong>the</strong>m, because <strong>of</strong> larger<br />
movements in <strong>the</strong> overall<br />
programme. For example, on <strong>the</strong><br />
assembly windows package <strong>the</strong><br />
satisfactory performance <strong>of</strong> <strong>the</strong> trade<br />
contractor was questioned<br />
throughout. The construction<br />
manager regularly wrote to <strong>the</strong> trade<br />
contractor to record dissatisfaction<br />
with progress <strong>of</strong> <strong>the</strong> works.<br />
However, <strong>the</strong> construction manager<br />
had to recommend a 42 week<br />
extension <strong>of</strong> time for <strong>the</strong> trade<br />
contractor when a new strategic<br />
programme was issued which<br />
extended <strong>the</strong> time period for<br />
completion by 42 weeks.<br />
Part 4. The reasons for increased costs 61