02.03.2013 Views

Management of the Holyrood building project (PDF ... - Audit Scotland

Management of the Holyrood building project (PDF ... - Audit Scotland

Management of the Holyrood building project (PDF ... - Audit Scotland

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

4.36 After construction started <strong>the</strong><br />

construction manager held regular<br />

design meetings, cost meetings and<br />

progress meetings for each package.<br />

However, <strong>the</strong> effectiveness <strong>of</strong><br />

management and control has almost<br />

certainly been compromised by <strong>the</strong><br />

strict requirement to adhere to<br />

programme targets that could be said<br />

to have been unachievable. Driving<br />

trade contractors to comply with<br />

unachievable programmes increases<br />

costs, in terms <strong>of</strong> prolongation costs<br />

and also in disruption costs.<br />

4.37 Eight <strong>of</strong> <strong>the</strong> 20 packages<br />

reviewed were awarded on <strong>the</strong> basis<br />

ei<strong>the</strong>r that <strong>the</strong> outstanding design<br />

would be completed within an<br />

agreed period after award or simply<br />

as quickly as possible. In <strong>the</strong>se<br />

cases, for coordination, <strong>the</strong><br />

construction manger ensured that a<br />

schedule was agreed that showed<br />

<strong>the</strong> latest dates that <strong>the</strong> trade<br />

contractor needed design information<br />

from <strong>the</strong> design team. Achievement<br />

<strong>of</strong> <strong>the</strong> design programme slipped<br />

from <strong>the</strong> agreed dates and this<br />

design slippage within individual<br />

packages contributed to <strong>the</strong> overall<br />

delay, as a delay on one package can<br />

affect o<strong>the</strong>r packages, and so on.<br />

4.38 Even where <strong>the</strong> performance <strong>of</strong><br />

trade contractors may not have been<br />

satisfactory, <strong>the</strong>re was in some<br />

cases little opportunity to attribute<br />

delays to <strong>the</strong>m, because <strong>of</strong> larger<br />

movements in <strong>the</strong> overall<br />

programme. For example, on <strong>the</strong><br />

assembly windows package <strong>the</strong><br />

satisfactory performance <strong>of</strong> <strong>the</strong> trade<br />

contractor was questioned<br />

throughout. The construction<br />

manager regularly wrote to <strong>the</strong> trade<br />

contractor to record dissatisfaction<br />

with progress <strong>of</strong> <strong>the</strong> works.<br />

However, <strong>the</strong> construction manager<br />

had to recommend a 42 week<br />

extension <strong>of</strong> time for <strong>the</strong> trade<br />

contractor when a new strategic<br />

programme was issued which<br />

extended <strong>the</strong> time period for<br />

completion by 42 weeks.<br />

Part 4. The reasons for increased costs 61

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!