Appendix 1. Trade Contract case studies 79<br />
Package Description Contractor Date <strong>of</strong> Basis <strong>of</strong> Cost Estimated<br />
contract appointment Plan outturn<br />
cost<br />
15 MSP <strong>building</strong><br />
windows and<br />
cladding<br />
– Mero Mar 02 Single stage £1.0m £2.8m<br />
16 Specialist Assembly <strong>building</strong>s Mero May 02 Negotiated £1.9m £11.0m<br />
glazing specialist glazing<br />
17 Hard Perimeter walls, O’Rourke Aug 02 Single stage £4.4m £5.6m<br />
landscaping roads, etc<br />
18 Assembly<br />
<strong>building</strong><br />
ro<strong>of</strong>lights<br />
– Space Decks Aug 02 Negotiated £0.2m £1.9m<br />
19 Zone 1 fit-out Fittings for chamber,<br />
towers 1 & 2, press<br />
tower<br />
Mivan Aug 02 Single stage £5.0m £14.1m<br />
20 Zone 2 fit-out Fittings for Canongate,<br />
foyer, towers 3 & 4<br />
Mivan Sep 02 Single stage £2.9m £7.8m<br />
Total £71.7m £152.5m<br />
Note: Cost Plan refers to <strong>the</strong> adjusted cost plan figure.<br />
The Estimated Outturn cost is <strong>the</strong> estimated final cost <strong>of</strong> <strong>the</strong> package including inflation but excluding risk elements.<br />
The combined risk element for <strong>the</strong> 20 packages is £40.3 million.<br />
Figures are rounded to <strong>the</strong> nearest £0.1 million.<br />
Source: <strong>Audit</strong> <strong>Scotland</strong>