LRO Open Risks<br />

LRO Risk: LOLA Laser Design Lifetime not Qualified by Lifetest Prior to Launch Risk ID: LOLA-261*<br />

Rank Risk Statement Approach & Plan Comments/Status<br />

1 Given The failure in the LOLA EM<br />

laser life test,<br />

Then: LOLA may not achieve the<br />

recommended 800 million shots<br />

necessary to meet its Level 1<br />

science requirements.<br />

M<br />

Mitigate:<br />

Examine and review why EM laser lifetest<br />

failed. Most likely cause established<br />

(failure of laser optics common to both<br />

lasers, possibly contamination induced).<br />

Laser 2 cavity undamaged. Rebuild<br />

common optics train and resume lifetest on<br />

Laser 2 only (complete, lifetest resumed<br />

9/19). In parallel, LRO to examine ways to<br />

extend flight laser lifetime operationally<br />

and plan to minimize the number of shots<br />

at the orbiter level pre-launch. Examples:<br />

automated safing to shut laser down if<br />

thermistor failure causes diode<br />

temperature increase.<br />

Additional Watch Plan: Monitor<br />

performance of rebuilt EM laser after<br />

resumption of testing. Make operational<br />

decisions based on performance during<br />

test.<br />

Contingency:<br />

Assuming Laser performance floor of 500<br />

million shots, LOLA science team to<br />

examine impact of more-limited lifetime on<br />

the LOLA L1 data products.<br />

In Progress:<br />

Apr 08: Root cause not established, effects (common optics<br />

damage, L1 diode heat sink burn marks) known. Possible ways to<br />

extend flight operational lifetime include safing, minimizing shots<br />

on ground & duty cycling lasers .<br />

May 08: As result of 5/31 LRO/LOLA risk assessment meeting,<br />

LRO and Proj. agree that LRO proposes to fly LOLA as-is, and<br />

will resume the EM laser lifetest ASAP, ensuring that the<br />

hardware is as flight-like as possible .<br />

Aug 08: Rebuild/retest of the EM laser currently on schedule to<br />

resume extended ops testing by end of Sept.<br />

Sept 08: Rebuild of the EM laser completed and extended vac<br />

testing has resumed. W/launch delay, there is time for the rebuild<br />

EM laser to reach 500 million shots by launch. Test results and<br />

risk assessment to be monitored monthly.<br />

Oct 08: As of 11/05, LOLA has accumulated 92 million shots in<br />

vacuum towards the goal of 500 million shots by 4/24/09. Laser<br />

performance is nominal.<br />

As of 12/01, LOLA EM laser has accumulated 152 Mshots in<br />

vacuum. Performance remains nominal (this includes normal<br />

increasing of the switch out time, which has increased from 170<br />

usec to 180 usec over the test to date).<br />

Dec 08: 219 Mshot in vac as of 12/24, switch out time still 180<br />

usec. Reassess likelihood when total number of shots hits 350-<br />

400 million shots, predicted by the end of March.<br />

Jan 09: As of 1/29, EM laser now at 304 million shots. All<br />

performance, including switch out time, remains nominal.<br />

Feb 09: As of 2/25, EM laser now at 366 million shots. All<br />

performance parameters remain nominal. Switchout time<br />

continuing slow, steady increase, but no changes to diode current<br />

setting have been performed to date.<br />

NASA’s Goddard Space Flight Center LRO Flight <strong>Operations</strong> <strong>Review</strong> (FOR) Day 1 - 38