A Guide Fire on Protection Fire Protection and Performance-based and Performance-based Fire Engineering Fire Engineering<br />
When are the Fire Safety Engineer (FSE) and Peer Reviewer required?<br />
The <strong>Building</strong> Developer should engage the FSE on the onset of building project involving<br />
performance-based works, during the conceptual design stage, and not as a remedial solution<br />
to resolve deadlocks in the approval process.<br />
The <strong>Building</strong> Developer should engage the Peer Reviewer only after the FSE has completed his<br />
Fire Safety Engineering Report (FSER), detailed specifications and drawings and the <strong>Building</strong><br />
Operations and Maintenance manual (O&M). It is important that the Peer Reviewer does not<br />
participate or interfere with the design process prior to this stage. The Peer Reviewer will make<br />
his comments in his Peer Reviewer’s Report. In the event that the Peer Reviewer has disagreeable<br />
comments on the documents reviewed, the FSE and the Peer Reviewer will need to discuss<br />
objectively to resolve the outstanding issues.<br />
The Project QP is responsible to submit all the mentioned documents to the Relevant <strong>Authority</strong><br />
for final plan approval.<br />