7.4. ECONOMIC IMPACTS<br />
Report No 678-F-001<br />
METSI CONSULTANTS: SUMMARY OF MAIN FINDINGS FOR PHASE 1 DEVELOPMENT<br />
The annual resource losses for the predicted reduction in riverine resources and the costs of mitigation of healthrelated<br />
impacts are shown in Table 7.3.<br />
7.5. WATER YIELD<br />
Table 7.3 Annual social losses and costs associated with<br />
the Design Limitation Scenario.<br />
Monetary Value<br />
Cost Type Component<br />
(Maloti)<br />
Resource losses* 1<br />
Mitigation Costs* 3<br />
Fish* 2 1,223,630<br />
Forage 52,617<br />
Medicinal plants 73,442<br />
Wild vegetables 497,030<br />
Trees & shrubs 3,681,018<br />
Sub-Total 5,527,737<br />
Public health 117,584<br />
Animal health 59,340<br />
Sub-Total 176,924<br />
Total 5,704,661<br />
* 1 Based on local trade values<br />
* 2 Total loss assumed for Reach 1 (Matsoku), proportional<br />
losses for other reaches<br />
* 3 Costs of avoiding health impacts<br />
The system yield (using an annual reliability of 98%) associated with the Design Limitation Scenario is estimated<br />
to be 22.8 m 3 s -1 .<br />
41