32 Chapter 1 Getting Started with <strong>Project</strong><br />
This date is now scheduled as nonworking time for the project. In the dialog box,<br />
the date appears underlined and is formatted teal to indicate an exception day.<br />
5. Click OK to close the Change Working Time dialog box.<br />
To verify the change to the project calendar, scroll the chart portion of the Gantt<br />
Chart view (the portion on the right) to the right until Monday, January 28, is visible.<br />
Like the weekends, January 28 is formatted gray to indicate nonworking time.<br />
Tip To learn more about calendars, type Overview of using calendars in <strong>Project</strong> into the<br />
box labeled Type a question for help.<br />
Entering <strong>Project</strong> Properties<br />
Like other <strong>Microsoft</strong> Offi ce programs, <strong>Project</strong> keeps track of several fi le properties. Some<br />
of these properties are statistics, such as how many times the fi le has been revised. Other<br />
properties include information you might want to record about a project plan, such as<br />
the project manager’s name or keywords to support a fi le search. <strong>Project</strong> also uses properties<br />
in page headers and footers when printing.<br />
In this exercise, you enter some properties that you will use later when printing project<br />
information and for other purposes.<br />
1. On the File menu, click Properties.<br />
Monday, January 28 is a nonworking day and<br />
is formatted in gray (as are weekends) in the<br />
Gantt chart<br />
The Properties dialog box appears.<br />
2. Click the Summary tab if it is not already visible.<br />
3. In the Subject box, type Video production schedule.<br />
4. In the Author box, type your name.<br />
5. In the Manager box, type your name, type your manager’s name, or leave the box<br />
blank.<br />
6. In the Company box, type Southridge Video.<br />
7. Select the Save preview picture check box.