Large blocks were produced from two soil mixtures to compare their compressive<br />

and flexural strengths. The soil mixes were amended with approximately 6% Portland<br />

cement for stabilization. Exact material quantities are reported in Tables 4.13 & 4.14.<br />

The “% Mass <strong>of</strong> Total Dry Soil Mix” was calculated to show the amount <strong>of</strong> each<br />

individual material in relation to the total mass <strong>of</strong> the dry soil mixture. After the dry<br />

materials were thoroughly mixed, water was added to reach a target range <strong>of</strong> 10-12%<br />

water content. A sample from each soil mixture was taken during block production to<br />

determine the actual water content which is reported in Tables 4.13 & 4.14.<br />

Material<br />

Soil #11: 1:3 Large-Block Composition Soil #15: 1:3 Large-Block Composition<br />

Dry Mass<br />

[lb]<br />

% Mass <strong>of</strong> Total<br />

Dry Soil Mix<br />

Material<br />

Dry Mass<br />

[lb]<br />

47<br />

% Mass <strong>of</strong> Total<br />

Dry Soil Mix<br />

Sand 383.1 70.8% Sand 279.0 70.8%<br />

Clayey Soil 127.7 23.6% Clayey Soil 93.0 23.6%<br />

Cement 30.6 5.7% Cement 22.3 5.7%<br />

Water Content 11.3% Water Content 10.0%<br />

Table 4.13<br />

Soil #11: 1:1 Large-Block Composition Soil #15: 1:1 Large-Block Composition<br />

Material<br />

Dry Mass<br />

[lb]<br />

% Mass <strong>of</strong> Total<br />

Dry Soil Mix<br />

Material<br />

Dry Mass<br />

[lb]<br />

% Mass <strong>of</strong> Total<br />

Dry Soil Mix<br />

Sand 187.1 47.2% Sand 172.7 47.2%<br />

Clayey Soil 187.1 47.2% Clayey Soil 172.7 47.2%<br />

Cement 22.5 5.7% Cement 20.7 5.7%<br />

Water Content 12.8% Water Content 12.5%<br />

Table 4.14<br />

4.2.2.3. Test Block Production<br />

The mini-blocks made from the soil mixes displayed in Table 4.11 & 4.12 ejected<br />

cleanly from the AECT Small Block Press and were immediately placed in a controlled<br />

environment after recording their initial weight and dimensions. The mini-blocks were<br />

observed 2-3 times per week during the initial 4 week curing period. No effects due to