25.10.2013 Views

Soil-Structure Interaction Seminar - Foundation Performance ...

Soil-Structure Interaction Seminar - Foundation Performance ...

Soil-Structure Interaction Seminar - Foundation Performance ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Inspections of the foundation had been made in 1988 and 1989 to assess cracking in<br />

the floor t i1 es. An inspection made in 1991, however, showed the presence of a<br />

significant amount of damage. The contour height measurements that were made during<br />

the 1991 inspection are shown in Figure 3. Obviously, the foundation had heaved<br />

upward along the rear wall. Testing showed that the contractor had failed to use a<br />

select fill, as specified. Of more significance, it was learned that the owner had<br />

a drain sump installed in the back yard. The drain pipe was routed to the drain<br />

line that the builder had previously installed at the edge of the foundation;<br />

however, the new pipe was never connected to the ori gina 1 pipe. As a result, any<br />

rainwater that was collected in the yard sump was routed directly to the edge of the<br />

fouhdation and hence down the sides of the piers.<br />

There were two errors which contributed to the problems with this foundation. One<br />

was the placement of the non-select fill; however, since the heaving was limited to<br />

the area where the non-select fill existed, once can but conclude that the-error in<br />

the placement of the fill was not the major contributor. To the best of our knowledge<br />

this foundation has yet to be repaired.<br />

CASE NO. 4 - CONSTRUCTION DEVIATIONS<br />

This was a two story residential building which was constructed in the early 1990's.<br />

The buHding plans showed the foundation to be a reinforced concrete, grade-beamstiffened,<br />

slab type supported on drilled piers. The soils were lcnown to be very<br />

expansive (3).<br />

The building began to develop some craclcing early in its life and, based on a recommendation<br />

from a foundation repair contractor, pressed piles were place under one of<br />

the front corners. The craclcing continued. The results of the foundation height<br />

measurements we made on this project are shown in Figure 4. The owner then hired an<br />

engineer and excavations were made at several locations around the perimeter of the<br />

building. Among other things, it was discovered that there were significant gaps<br />

between the top of the piers and the bottom of the grade beams - some gaps being as<br />

wide as one foot. The foundation grade beams were also found to be of a height that<br />

was somewhat less than specified. No meaningful data were acquired that would lead<br />

to any conclusions with regard to the placement of the reinforcing steel.<br />

The builder then agreed to have the foundation repaired. Bids were acquired to have<br />

the foundation underpinned using pressed piles with the interior piles being placed<br />

using tunneling techniques. A question was raised concerning the potential vertical<br />

rise of the soil near the center of the foundation. The soH testing showed the<br />

moisture content of the soil to be 6 to 10 percent above the plastic limit. It was<br />

concluded that the soil under the slab was near an equilibrium moisture content; however,<br />

there was also a concern that the potential vertical rise could be as much as<br />

4 inches. The foundation repair contractor was aslced to revise his bid to include<br />

raising the entire foundation 4 inches. This bid was equal to approximately 50% of<br />

the cost of the original construction. It was then decided that stabilization would<br />

be achieved using a vertical moisture barrier. The design of this barrier is shown<br />

in Figure 4. The builder agreed to also underpin the foundation around the perimeter<br />

and under the interior of the foundation where point loads existed; however,<br />

no serious attempt was made to raise the foundation any significant amount. The<br />

vertical moisture barrier was installed with the total cost being approximately 50%<br />

of the bid cost to raise the building 4 inches. The long-term results are yet to be<br />

assessed.<br />

-3-

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!