Temporary Bridge – Performance Metrics<br />
Conventional Delivery<br />
•$2,100,000 to construct<br />
•4-6 months disruption<br />
of entry<br />
Prefabricated Delivery<br />
•$980,000 to construct<br />
•3 days of construction<br />
not disruption<br />
•Overnight removal of<br />
bridge after completion of<br />
permanent connector –<br />
zero disruption to campus<br />
and worksite<br />
2011 NYC Healthcare Symposium<br />
10/27/2011<br />