• Details of parameters of Electronics/Electrical/Mechanical appliances used in the plant.<br />

• Addresses of the OEM’s and the suppliers of the equipment fitted in the plant. This should<br />

also be supplied in the form of a Bill of m<strong>at</strong>erials in MS Excel, MS Access form<strong>at</strong>s on<br />

suitable electronic media.<br />

<strong>Supply</strong> of Spares :<br />

The firm shall have to ensure th<strong>at</strong> spares for the maintenance of this plant and the<br />

equipment fitted there in are supplied (on payment basis) to the Diesel Shed as and when<br />

required for a minimum period of five years after the expiry of the warranty period.<br />

Electrical Works :<br />

Contactor shall have to carry out the work of laying of electrical cables for all the<br />

electrical work involved in the ETP. Diesel shed will provide incoming electrical supply <strong>at</strong> the<br />

MCTB. Tenderer will have to supply all the electrical controls, energy meters, bus bars etc. for<br />

oper<strong>at</strong>ing the plants. The firm will have to supply the m<strong>at</strong>erial as per list enclosed <strong>at</strong> annexure<br />

B1 & B2.<br />

Civil Works :<br />

Tenderer will have to carry out all civil engineering works for all types of tanks and<br />

chambers etc. required in the plant as per standard specific<strong>at</strong>ion. They shall also submit<br />

detailed engineering drawings of all the engineering works of the plant certified by some<br />

qualified consultant.<br />

Sub-Contracted equipment :<br />

All the sub-Contracted equipment should be covered with a warranty for<br />

repair/replacement. Manuals & sources of spares required for the maintenance of these<br />

equipment should also be supplied for all sub-contracted equipment.<br />

Warranty :<br />

All the items / equipments fitted and all the works done in the plant must be under<br />

warranty for a minimum period of 24 months from the d<strong>at</strong>e of commissioning and the final<br />

acceptance of the plant. During this period the contractor is liable to arrange for immedi<strong>at</strong>e<br />

repairs/replacement of the defective parts/equipment free of cost and put the equipment in to<br />

normal working order within 03 days from the d<strong>at</strong>e of sending inform<strong>at</strong>ion to the contractor.<br />

Such replacement shall further carry a warranty of two year and a half from the d<strong>at</strong>e of<br />

replacement/repair.<br />

Acceptance Test :<br />

Tender is required to submit the details of the test procedures to be followed for<br />

commissioning and oper<strong>at</strong>ion of the effluent tre<strong>at</strong>ment plants <strong>at</strong> the <strong>site</strong> of install<strong>at</strong>ion<br />

indic<strong>at</strong>ing the dur<strong>at</strong>ion of the test period and shall warranty an average up time efficiency of<br />

90% for the dur<strong>at</strong>ion of the test period.<br />

The scope details, dur<strong>at</strong>ion and extension if any of the acceptance shall be discussed<br />

and mutually agreed upon between the purchaser and the contractor.<br />

On receipt of the advice from the contractor th<strong>at</strong> the system has been installed and is<br />

ready for acceptance test, one acceptance test of the effluent tre<strong>at</strong>ment plant shall be conducted<br />

by the contractor in the presence of Sr. Divisional Mechanical Engineer (Diesel)/N.E. Railway,<br />

Gonda or his authorized represent<strong>at</strong>ive.<br />

The contractor <strong>at</strong> his own cost shall provide any special equipment and tools required<br />

for the acceptance test. Railways will provide necessary electric power free of cost to enable<br />

the contractor to carry out this test. The test shall be conducted as stipul<strong>at</strong>ed here under.<br />

The contractor shall maintain necessary log book in respect of the result of the test to<br />

establish entire s<strong>at</strong>isfaction of the purchaser, the successful completion of the test specified.<br />