Verific<strong>at</strong>ion of antecedents of the personnel :<br />
Page 28 of 34<br />
The contractor should engage the labour whose character and antecedents have been<br />
verified before they are utilized to work in Railway in the event of any staff of the contractor<br />
being found indulging in external activities, the contractor shall be liable for the same and<br />
further if the Railway administr<strong>at</strong>ion on inquiry comes to know th<strong>at</strong> proper verific<strong>at</strong>ion of the<br />
antecedents was not carried out by the contractor in case of the labour employed by him, this<br />
contract will be liable to be termin<strong>at</strong>ed forth with.<br />
Acceptance of additional conditions proposed by the tenderer :<br />
Any condition of the tender other than those stipul<strong>at</strong>ed in the documents are not<br />
applicable even through they are included in the tender submitted by the party unless they are<br />
specifically accepted by the Railway in writing while communic<strong>at</strong>ing the acceptance of the<br />
tender. The successful tenderer should therefore ensure th<strong>at</strong> the Railway before accepting the<br />
offer should accept such conditions th<strong>at</strong> are considered necessary by him. This acceptance<br />
must be obtained in written form<strong>at</strong>.<br />
Vari<strong>at</strong>ion of scope of work :<br />
Changes in scope of work will be done after mutual consider<strong>at</strong>ion and agreement.<br />
Changes in scope of work under normal circumstances shall not exceed 25% of a total value of<br />
contract. Changes in excess of scope of work exceeding 25% of a total cost will be dealt<br />
separ<strong>at</strong>ely from this contract.<br />
Modific<strong>at</strong>ion of contract :<br />
Sr. Divisional Mechanical Engineer (Diesel)/N.E. Railway, Gonda reserves the rights to<br />
reject/accept the whole or part of the offer or for the portion of the quantity indic<strong>at</strong>ed in the<br />
offer without assigning any reason there upon and the right to open the negoti<strong>at</strong>ion and to call<br />
for the revised offer, or to alter or to modify and of conditions or to incorpor<strong>at</strong>e any new<br />
conditions as found necessary till the contract is finally executed. All decisions and behalf of<br />
the Railway administr<strong>at</strong>ion will be taken up by Sr. Divisional Mechanical Engineer<br />
(Diesel)/N.E. Railway, Gonda and shall be final and binding on the contractor.<br />
M<strong>at</strong>ter finally decided by the Railway ;<br />
All dispute and differences of any kind wh<strong>at</strong> so ever arising out of or in connection<br />
with the contract whether during the progress of the works or after the completion and whether<br />
before or after determin<strong>at</strong>ion of the contract shall be decided by the Sr. Divisional Mechanical<br />
Engineer (Diesel)/N.E. Railway, Gonda.<br />
The decision, direction & certific<strong>at</strong>e with respect to any m<strong>at</strong>ters, the decision of which<br />
is specifically provided of by these or other special condition, given and made by Sr.<br />
Divisional Mechanical Engineer (Diesel)/N.E. Railway, Gonda be referred herein after as<br />
“Excepted m<strong>at</strong>ter” and shall be final and binding upon the contractor and shall not be set aside<br />
on any account of any informality or omission delay or error in proceeding in or about the<br />
same or any other ground or for any other reason.<br />
Arbitr<strong>at</strong>ion :<br />
Any dispute arising between the parties of contract shall be settled through arbitr<strong>at</strong>ion<br />
as per arbitr<strong>at</strong>ion clause 62, 63 & 64 of the GCC 1999. The provision of GCC arbitr<strong>at</strong>ion &<br />
concili<strong>at</strong>ion act 1996 shall be applicable.<br />
Termin<strong>at</strong>ion of the contract :<br />
The Sr. Divisional Mechanical Engineer (Diesel)/N.E. Railway, Gonda or his<br />
authorized represent<strong>at</strong>ive reserves the right to termin<strong>at</strong>e the contract <strong>at</strong> any stage without<br />
assigning any reason wh<strong>at</strong>soever after serving one month’s notice to the contractor.