Min 1.0m from edge <strong>of</strong> trench<br />

Level ground /undisturbed surface<br />

or if disturbed, to be compacted to 100%<br />

S.P.M.D.D. <strong>and</strong> soil bearing capacity<br />

to be measured<br />

=l<br />

Unshrinkable fill, minimum<br />

0.6m below existing pipe<br />

up to centreline. Depth <strong>of</strong><br />

unshrinkable fillto be<br />

determined based on<br />

size <strong>of</strong> existing wm,<br />

Trenching to comply<br />

with M.O.L. guidelines,<br />

Existing ground<br />

Existing <strong>Water</strong>main<br />

Cut into side slopes<br />

0.6m in order to place<br />

unshrinkable fill<br />

Granular bedding<br />

to be installed to<br />

<strong>City</strong> <strong>of</strong> <strong>London</strong> St<strong>and</strong>ards.<br />

Proposed pipe to<br />

cross existing wm.<br />

label elevation <strong>of</strong><br />

pipe invert.<br />

WPICAL REINSTATEMENT /BEDDING DETAIL CROSS SECTION<br />

SEE DRAWING W-CS-69,_<br />

SHEET 3 FOR REQUIREMENTS<br />

Verify &<br />

lableldepth<br />

The watermain shall be protected by the following:<br />

- When crossing under or over the watermain there must be a<br />

minimum separation <strong>of</strong> at least 0.6m between the outside<br />

diameters <strong>of</strong> the crossing pipes.<br />

- A minimum 5.0m length <strong>of</strong> pipe shall be centered at the point<br />

<strong>of</strong> crossing so that the watermain joints will be equidistance<br />

<strong>and</strong> as far as possible from the sewer or PDC. Crossing must<br />

be absolute minimum 2.0m from watermain joint.<br />

- All construction methods including excavation <strong>and</strong> backfill<br />

compaction within 0.6m <strong>of</strong> existing watermain shall be done by<br />

h<strong>and</strong>.<br />

It should be noted that the support structure is to remain in<br />

place until the watermain is fully supported by the reinstated<br />

bedding (i.e, until SMPa unshrinkable fill is cured, provide bond<br />

break).<br />

CITY OF LONDON STANDARD DRAWING<br />

TYPICAL REINSTATEMENT /BEDDING DETAIL<br />

FOR 450mm AND UP WATERMAIN SUPPORT