Name of Respondent<br />

This Report Is:<br />

Date of Report<br />

(1) X An Original<br />

(Mo, Da, Yr)<br />

PACIFIC GAS AND ELECTRIC COMPANY<br />

(2) A Resubmission<br />

04/08/2011<br />

CONSTRUCTION WORK IN PROGRESS - - ELECTRIC (Account 107)<br />

Year/Period of Report<br />

End of <strong>2010</strong>/Q4<br />

1. Report below descriptions <strong>and</strong> balances at end of year of projects in process of construction (107)<br />

2. Show items relating to "research, development, <strong>and</strong> demonstration" projects last, under a caption Research, Development, <strong>and</strong> Demonstrating (see<br />

Account 107 of the Uniform System of Accounts)<br />

3. Minor projects (5% of the Balance End of the Year for Account 107 or $1,000,000, whichever is less) may be grouped.<br />

Line<br />

No.<br />

1<br />

2<br />

3<br />

4<br />

5<br />

6<br />

7<br />

8<br />

9<br />

10<br />

11<br />

12<br />

13<br />

14<br />

15<br />

16<br />

17<br />

18<br />

19<br />

20<br />

21<br />

22<br />

23<br />

24<br />

25<br />

26<br />

27<br />

28<br />

29<br />

30<br />

31<br />

32<br />

33<br />

34<br />

35<br />

36<br />

37<br />

38<br />

39<br />

40<br />

41<br />

42<br />

Description of Project Construction work in progress -<br />

<strong>Electric</strong> (Account 107)<br />

(a)<br />

(b)<br />

5738901 McMullin-Kearney 230 kV Reconductor<br />

1,925,226<br />

5733245 Trans Rep Wood Poles_EPC Contract<br />

1,913,611<br />

5737998 COM:Unattended Pathway<br />

1,855,248<br />

5722499 Fort Ord Substation, Bus Regulator<br />

1,852,422<br />

5726809 Atwater Bank 1 115kv-12kv, 45 MVA LTC<br />

1,843,819<br />

5735945 Madera MPAC<br />

1,833,353<br />

5734001 Henrietta Sub: Install New Bank<br />

1,825,225<br />

5736134 Tulare Lake Sub: Inst new Bank<br />

1,797,171<br />

5506253 JIT Replace Transformers<br />

1,796,299<br />

5733990 Glenn Sub: Install Bank 3<br />

1,789,743<br />

5731018 Tesla - Salado - Manteca 115 kV Reconductor<br />

1,771,507<br />

5722558 DeSabla Philbrook Refurb. Spill Channel<br />

1,768,838<br />

5727142 Belmont Sub:Repl 115-12kV Bank2<br />

1,748,951<br />

5506282 JIT Replace Miscellaneous Equipment<br />

1,743,488<br />

5733504 Divide 115 kV MPAC<br />

1,741,198<br />

5733513 Bellota 115 kV MPAC<br />

1,736,693<br />

5505580 Work at the Request of Others Partially Reimb.-CC<br />

1,684,865<br />

5732691 Brighton 115 kV MPAC<br />

1,670,426<br />

5724539 Helm - Replace Exciters<br />

1,663,941<br />

5503191 Mission-City Reliability<br />

1,610,092<br />

5717279 Work at the Request of Others Rule 20A - De Anza<br />

1,579,302<br />

5724399 Drum 1&2 Penstock Tunnel Replacement<br />

1,568,726<br />

5733929 Replace Clayton Bank #1 <strong>and</strong> new feeder<br />

1,550,034<br />

5732978 Sacramento-Caribou#1 60kVBusRecon&SCADAIns<br />

1,543,407<br />

5732986 Moss L<strong>and</strong>ing: convert 230 kV bus to BAAH<br />

1,542,536<br />

5729171 Yosemite Madera: Install Bank/Feeder<br />

1,538,937<br />

5733803 Pease Sub: Repl Failed Reg #2<br />

1,530,445<br />

5738220 Wheeler Ridge 70 kV MPAC<br />

1,503,886<br />

5738000 COM:Last Access Control<br />

1,499,144<br />

5733933 Instll Nortch Bnk#2 for Cisco Sys Exp<br />

1,493,031<br />

5707549 Windsor Sub: L<strong>and</strong> (Fulton DPA)<br />

1,489,917<br />

5727860 U1:Replace Eagle-21 System (I&COM)<br />

1,438,277<br />

5720874 Balch 2 U3 Replace Exciter<br />

1,431,518<br />

5720780 Pit 345 LC Recreation<br />

1,428,387<br />

5726838 U1:Mod Control Room Ventilation<br />

1,428,291<br />

5724538 Helms - Replace Governors<br />

1,414,391<br />

5739631 BURNS 60/24 KV, 10 MVA, BK 1 Emerge<br />

1,410,711<br />

5738728 Cottle MPAC 230kv<br />

1,407,339<br />

5732985 Moss L<strong>and</strong>ing: convert 115 kV bus to BAAH<br />

1,395,097<br />

5730184 Wheeler Ridge 230/70 kV Transfor Install<br />

1,363,754<br />

5731362 Hydro SCADA - Life Cycle Replacement<br />

1,363,482<br />

5726618 Newark-Ravenswood 230kV Reconductor<br />

1,361,372<br />

43 TOTAL 1,016,902,985<br />

<strong>FERC</strong> FORM NO. 1 (ED. 12-87) Page 216.3