20.06.2014 Views

SOUTHSIDE INDEPENDENT SCHOOL DISTRICT - San Angelo ISD

SOUTHSIDE INDEPENDENT SCHOOL DISTRICT - San Angelo ISD

SOUTHSIDE INDEPENDENT SCHOOL DISTRICT - San Angelo ISD

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

9.8.3 Add new Clause 9.8.3.1 and 9.8.3.2 to Section 9.8.3 as follows:<br />

.1 If, in Architect's opinion during the inspection, the Project or the designated portion thereof<br />

which Owner has agreed to accept separately is not sufficiently complete to warrant<br />

inspection, or if the list of items to be completed or corrected is not sufficiently complete to<br />

warrant inspection, then Architect may terminate the inspection and notify the Contractor<br />

that the Project is not ready for inspection. If for such reasons, Architect is required to make<br />

additional inspections, the Owner may deduct the cost of Architect's additional services<br />

made necessary thereby from any payments due the Contractor. The Architect’s<br />

compensation shall be determined in accordance with the applicable provisions of the<br />

Owner-Architect Agreement.<br />

.2 Except with the consent of the Owner, the Architect will perform no more than ONE (1)<br />

inspection to determine whether the Work has attained substantial Completion in<br />

accordance with the Contract Documents. The Owner shall be entitled to deduct from the<br />

Contract Sum amounts paid to the Architect, Engineer, Consultant or service provider for<br />

any additional inspections.<br />

9.8.4 Delete AArchitect@ in Section 9.8.4 and replace with AArchitect and Owner.@<br />

9.8.5 Delete the second and third sentences of Section 9.8.5 in their entirety.<br />

9.8.6 Add new Section 9.8.6 as follows:<br />

Retainage is not due to the contractor until thirty (30) days after Final Completion of the Work<br />

as set out in Section 9.10. After the Certificate of Substantial Completion is accepted by the<br />

Owner, the Owner may, in its sole discretion and upon acceptance and consent of surety, make<br />

payment of retainage on all or a part of the Work accepted.<br />

9.9.3 Delete Section 9.9.3 in its entirety and replace with the following:<br />

Unless expressly agreed upon in writing, partial occupancy or use of a portion or portions of the<br />

Work shall not constitute acceptance of Work not complying with the requirements of the<br />

Contract Documents.<br />

9.10.1 Delete Section 9.10.1 in its entirety and replace with the following:<br />

When all of the Work is finally completed and the Contractor is ready for a final inspection it<br />

shall notify the Owner and the Architect thereof in writing. Thereupon, the Architect and Owner<br />

will make final inspection of the Work and, if the Work is complete in full accordance with this<br />

Contract and this Contract has been fully performed, the Architect will promptly issue a final<br />

Certificate for Payment certifying to the Owner that the Project is complete and the Contractor<br />

is entitled to the remainder of the unpaid Contract Price, less any amount withheld pursuant to<br />

this Contract. Except with the consent of the Owner, the Architect will perform no more than<br />

one (1) inspection to determine whether the Work has attained Final Completion in accordance<br />

with the Contract Documents. If the Architect is unable to issue its final Certificate for Payment<br />

and is required to repeat its final inspection of the Work, the Contractor shall bear the cost of<br />

such repeat final inspection(s) which cost may be deducted by the Owner from the<br />

Contractor=s final payment.<br />

9.10.2 Delete the Section 9.10.2 in its entirety and replace with the following:<br />

The Contractor shall not be entitled to final payment unless and until it submits to the Architect<br />

its affidavit that the payrolls, invoices for materials and equipment, and other liabilities<br />

connected with the Work for which the Owner, or the Owner=s property, might be responsible<br />

have been fully paid or otherwise satisfied; releases and waivers of liens from all contractors of<br />

the Contractor and of any and all other parties required by the Architect or the Owner; such<br />

other provisions as Owner may request; and consent of Surety to final payment. If any third<br />

party fails or refuses to provide a release of claims or waiver of lien as required by Owner, the<br />

Contractor shall furnish a bond satisfactory to the Owner to discharge any such lien or<br />

indemnify the Owner from liability.<br />

Request for Proposals – CMAR Page 47 of 68 Rev 01/22/09<br />

<strong>San</strong> <strong>Angelo</strong> – Holiman Elementary

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!