! Petitioner would comply with all applicable Federal, state and local regulations regarding<br />
fugitive dust and open burning.<br />
! Petitioner would observe all applicable regulations for handling and disposing of waste<br />
materials, including hazardous waste.<br />
! Petitioner would restore any adjacent properties that are disturbed during construction.<br />
! Petitioner would use BMPs to control erosion, runoff and surface instability during construction.<br />
After the new rail line is constructed, NS will reseed outside the subgrade slope to provide<br />
permanent cover and prevent potential erosion.<br />
! Petitioner would control temporary noise from construction equipment by ensuring all<br />
machinery has properly functioning muffler systems and by work hour controls.<br />
! Petitioner would transport all hazardous materials in compliance with the DOT Hazardous<br />
Materials Regulations (49 CFR parts 171, 172, 173, 178, 179, 180, and 185).<br />
! In the case of a spill, Petitioner would follow appropriate emergency response procedures<br />
outlined in its emergency response plans.<br />
! Petitioner would restore all roads disturbed during construction to the conditions required by state or local<br />
regulations.<br />
5.3 SEA RECOMMENDED MITIGATION<br />
SEA recommends that the Board impose the following mitigation measures in any decision approving<br />
the construction waiver for the proposed rail line connection construction in Bucyrus.<br />