Souvenir - Bangladesh Group of IABSE
Souvenir - Bangladesh Group of IABSE
Souvenir - Bangladesh Group of IABSE
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
At the start <strong>of</strong> construction a substantial dredging and filling operation was undertaken to bring the area<br />
within the project land boundary to a level above the 1998 peak flood level and to provide fill material to the<br />
bridge approach road embankments.<br />
Before the new bridge was built, road traffic crossed the river by ferry, which <strong>of</strong>ten delay due to traffic<br />
problems or river conditions. In 1995, a commitment was made by the <strong>Bangladesh</strong> government to improve<br />
communications to stimulate the north-east region and provide a road bridge across the Meghna between<br />
Bhairab and Ashuganj. In parallel, the existing Dhaka-Sylhet road was to be upgraded over its entire<br />
length. A series <strong>of</strong> economic, social and engineering studies for the crossing were carried out. The<br />
economics and need for the crossing were verified by the studies.<br />
In 1997 a study was carried out on behalf <strong>of</strong>the UK Department for International Development (DFID) and<br />
the Government <strong>of</strong> <strong>Bangladesh</strong> in which various aspects <strong>of</strong> the proposed bridge crossing were appraised<br />
and recommendations were given for the design and construction <strong>of</strong> a new crossing.<br />
The report concluded that a new dual two lane multi-span bridge should be constructed at Bhairab,<br />
approximately 110m upstream <strong>of</strong> an existing steel truss railway bridge built over sixty years ago. The<br />
proposed project should also include the construction <strong>of</strong> new highway approach embankments and<br />
connecting roads and the provision <strong>of</strong> river training works and bank protection.<br />
The report also concluded that procurement <strong>of</strong> the bridge should be by the design and build route, let under<br />
the FIDIC Conditions <strong>of</strong> Contract for Design, Build and Turnkey.<br />
Following a decision by the Government <strong>of</strong> <strong>Bangladesh</strong> supported by DFID to proceed with the<br />
construction <strong>of</strong>the Bhairab Bridge Project, Halcrow was appointed Employer's Representative in August<br />
1998 for Phase 1 <strong>of</strong> the project. This involved surveys and investigations, preparation <strong>of</strong>tender documents,<br />
including firm design requirements, assisting with prequalification <strong>of</strong> contractors and evaluation <strong>of</strong><br />
contractor's tender submissions. To confirm the selected route alignment and to provide the maximum<br />
freedom to the tenderer's designs, preliminary geotechnical, bathymetric and topographic surveys together<br />
with mathematical and physical modeling <strong>of</strong>the river were carried out as part <strong>of</strong> the Phase 1 activities. The<br />
land acquisition requirements for the project were also determined in this phase and a Social Action Plan to<br />
mitigate adverse impacts was formulated in accordance with Government <strong>of</strong> <strong>Bangladesh</strong> and Organization<br />
for Economic Corporation and Development (OECD) guidelines.<br />
Contract documents for a design and build contract based on the FIDIC Orange Book conditions for<br />
international design and build contracts were issued at the end <strong>of</strong> 1998 to five prequalified UK contractors.<br />
Tenders were submitted in Spring, 1999 and a contract for the design and construction <strong>of</strong>Bhairab Bridge<br />
was awarded to Edmund Nuttal Ltd <strong>of</strong> UK with Jacobs, Benaim and DDC as their designer team. The<br />
project commencement date was 3November 1999.