11.11.2014 Views

Natomas Levee Improvement Program - SAFCA

Natomas Levee Improvement Program - SAFCA

Natomas Levee Improvement Program - SAFCA

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

3.8 Reach H (NEMDC between NEMDC Pump Station and Northgate Blvd)<br />

Reach H extends for 23,700 feet along the NEMDC west levee between <strong>SAFCA</strong>’s NEMDC<br />

Stormwater Pumping Station and Northgate Boulevard. <strong>SAFCA</strong>’s 200-year project in this reach<br />

includes installing cutoff walls in several portions of the levee; constructing bank protection<br />

improvements; relocating several water, gas and electrical lines through the levee; relocating a<br />

small number of electrical utility poles and lines at the landside toe of the levee; and<br />

reconstructing the bicycle trail on top of the levee. This work will be completed as part of the<br />

USACE project.<br />

3.8.1 Fish and Wildlife Facilities<br />

The 200-year project in this reach will have relatively minor impacts on various fish and<br />

wildlife habitats. Compensation for these impacts will be provided through construction<br />

of fish and wildlife facilities in Reach H. <strong>SAFCA</strong>’s estimate of the cost of these facilities<br />

reflects projected land acquisition; site preparation, planting and establishment costs; and<br />

long-term management costs derived from estimates prepared by <strong>SAFCA</strong>’s landscape<br />

management consultants. This land acquisition and site preparation costs include a 10<br />

percent contingency.<br />

The USACE estimate is significantly higher than <strong>SAFCA</strong>’s estimate and likely reflects<br />

the much larger project footprint anticipated by USACE in this reach.<br />

3.8.2 <strong>Levee</strong>s and Floodwalls<br />

<strong>SAFCA</strong>’s estimate for levee and floodwall construction in this reach includes costs for<br />

waterside rock slope protection. The estimate is based on the design consultant’s opinion<br />

of probable cost based on a 60 percent design and includes a 25 percent contingency.<br />

The <strong>SAFCA</strong> estimate assumes that levee construction in this reach will require<br />

approximately 0.1 million cubic yards of borrow material. This material will be obtained<br />

from the Krumenacher borrow site. The cost of this borrow material is approximately<br />

$0.3 million reflecting the cost of acquiring the right to take this material. The cost to<br />

acquire the right to take this material for borrow includes a 10 percent contingency.<br />

The USACE estimate for this work is almost three times higher than <strong>SAFCA</strong>’s estimate<br />

including contingencies. This likely reflects the larger project footprint assumed in the<br />

USACE estimate as well as differences in labor and materials costs, contractor mark-ups,<br />

and other cost items.<br />

3.8.3 Interior Drainage Pumping Plants<br />

RD 1000’s Pumping Plant 8 and the City of Sacramento’s Pumping Station 102 located<br />

along the NEMDC west levee in Reach H need to be reconstructed to accommodate the<br />

levee improvements in this reach. The reconstruction will occur as part of the USACE<br />

project. <strong>SAFCA</strong>’s estimate of the cost of this work reflects the design consultant’s<br />

opinion of the probable cost based on a 60 percent design plus a 25 percent contingency.<br />

The USACE estimate for this reconstruction work is slightly higher than <strong>SAFCA</strong>’s.<br />

Given the enlarged footprint of the NED Plan in this reach, the basis for this difference is<br />

unclear.<br />

34

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!