Natomas Levee Improvement Program - SAFCA
Natomas Levee Improvement Program - SAFCA
Natomas Levee Improvement Program - SAFCA
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
3.8 Reach H (NEMDC between NEMDC Pump Station and Northgate Blvd)<br />
Reach H extends for 23,700 feet along the NEMDC west levee between <strong>SAFCA</strong>’s NEMDC<br />
Stormwater Pumping Station and Northgate Boulevard. <strong>SAFCA</strong>’s 200-year project in this reach<br />
includes installing cutoff walls in several portions of the levee; constructing bank protection<br />
improvements; relocating several water, gas and electrical lines through the levee; relocating a<br />
small number of electrical utility poles and lines at the landside toe of the levee; and<br />
reconstructing the bicycle trail on top of the levee. This work will be completed as part of the<br />
USACE project.<br />
3.8.1 Fish and Wildlife Facilities<br />
The 200-year project in this reach will have relatively minor impacts on various fish and<br />
wildlife habitats. Compensation for these impacts will be provided through construction<br />
of fish and wildlife facilities in Reach H. <strong>SAFCA</strong>’s estimate of the cost of these facilities<br />
reflects projected land acquisition; site preparation, planting and establishment costs; and<br />
long-term management costs derived from estimates prepared by <strong>SAFCA</strong>’s landscape<br />
management consultants. This land acquisition and site preparation costs include a 10<br />
percent contingency.<br />
The USACE estimate is significantly higher than <strong>SAFCA</strong>’s estimate and likely reflects<br />
the much larger project footprint anticipated by USACE in this reach.<br />
3.8.2 <strong>Levee</strong>s and Floodwalls<br />
<strong>SAFCA</strong>’s estimate for levee and floodwall construction in this reach includes costs for<br />
waterside rock slope protection. The estimate is based on the design consultant’s opinion<br />
of probable cost based on a 60 percent design and includes a 25 percent contingency.<br />
The <strong>SAFCA</strong> estimate assumes that levee construction in this reach will require<br />
approximately 0.1 million cubic yards of borrow material. This material will be obtained<br />
from the Krumenacher borrow site. The cost of this borrow material is approximately<br />
$0.3 million reflecting the cost of acquiring the right to take this material. The cost to<br />
acquire the right to take this material for borrow includes a 10 percent contingency.<br />
The USACE estimate for this work is almost three times higher than <strong>SAFCA</strong>’s estimate<br />
including contingencies. This likely reflects the larger project footprint assumed in the<br />
USACE estimate as well as differences in labor and materials costs, contractor mark-ups,<br />
and other cost items.<br />
3.8.3 Interior Drainage Pumping Plants<br />
RD 1000’s Pumping Plant 8 and the City of Sacramento’s Pumping Station 102 located<br />
along the NEMDC west levee in Reach H need to be reconstructed to accommodate the<br />
levee improvements in this reach. The reconstruction will occur as part of the USACE<br />
project. <strong>SAFCA</strong>’s estimate of the cost of this work reflects the design consultant’s<br />
opinion of the probable cost based on a 60 percent design plus a 25 percent contingency.<br />
The USACE estimate for this reconstruction work is slightly higher than <strong>SAFCA</strong>’s.<br />
Given the enlarged footprint of the NED Plan in this reach, the basis for this difference is<br />
unclear.<br />
34