HYLOAD DPC AND CAVITY TRAY SYSTEMS 21<br />

Concrete wall<br />

tanking/DPC link detail<br />

Ruberoid High<br />

Performance DPC<br />

Ruberoid Plasprufe<br />

2000SA membrane<br />

Cavity fill<br />

Ruberoid Self-Adhesive<br />

Primer<br />

<strong>Hyload</strong> DPC Jointing Tape<br />

on Ruberoid Self Adhesive<br />

Primer<br />

Ruberoid High<br />

Performance DPC<br />

<strong>Hyload</strong> DPC Jointing Tape<br />

Ruberoid Self<br />

Adhesive Primer<br />

Ruberoid Plasprufe Protection Board<br />

Ruberoid Plasprufe 2000SA membrane<br />

Ruberoid Column Preformed<br />

Cloak Unit<br />

<strong>Hyload</strong> DPC Mastic<br />

<strong>Hyload</strong> DPC Jointing System<br />

Steel column<br />

Ruberoid High<br />

Performance DPC<br />

DPCs must project 5 mm beyond<br />

the external face and must be<br />

bedded on both faces with<br />

mortar.<br />

All joints between lengths of DPC,<br />

and DPC and Preformed Cloak<br />

Units must be lapped a minimum<br />

of 100 mm and bonded with<br />

<strong>Hyload</strong> DPC Lap Adhesive or<br />

<strong>Hyload</strong> DPC Jointing Tape.<br />

The cavity tray should step down<br />

or slope across the cavity not less<br />

than 150 mm towards the<br />

external leaf.<br />

Insulation omitted for clarity.<br />

Technical hotline: 0800 587 7391 www.ruberoid.co.uk