(c) Riot, commotion, disorder, strike or lockout by persons other than the<br />
contractor’s personnel and other employees of the contractor and<br />
subcontractors,<br />
(d) Munitions of war, explosive materials, ionizing radiation or<br />
contamination by radio activity, except as may be attributable to the<br />
contractor’s use of such munitions, explosives, radiation or radioactivity,<br />
and<br />
(e) Natural catastrophes such as earthquake, hurricane, typhoon or volcanic<br />
activity.<br />
(ii) Storm, to the extent that it could not reasonably have been expected to occur at<br />
the place, at the time of year, in question;<br />
(iii)Epidemic, famine;<br />
(iv) Strikes or boycotts interrupting supplies and services to the site (excluding strikes<br />
or boycotts by employees, agents or representatives of contractor, or its<br />
subcontractors for any reason whatsoever);<br />
(v) Fire caused otherwise than by any act or omission on the part of the contractor or<br />
its agents servants or employees or its subcontractor;<br />
(vi) Any event or circumstance of a nature analogues to any of the above or an Act of<br />
God.<br />
Obligation of the Parties to perform<br />
The obligations and liabilities of the contractor under this Contract would continue as<br />
long as the performance is not impeded by Force Majeure Event as defined above.<br />
The contractor shall resume performance of its obligations under this Contract as<br />
soon as possible after the Force Majeure Event no longer exists. Provided that the<br />
performance of the contractor’s obligations and liabilities shall, for the period of<br />
Force Majeure, be governed as per and be subject to the provisions of this clause.<br />
<strong>No</strong>tice<br />
The contractor if affected by the Force Majeure Event shall give notice to the<br />
employer in writing of the occurrence of any of the Force Majeure Event as soon as<br />
the same arises, and in any event within three (3) days after the knowledge by the<br />
contractor.<br />
<strong>No</strong>tice shall inter-alia include full particulars of –<br />
i) the nature of each Force Majeure Event<br />
ii) the date and time effective when the performance of contractor’s obligations under<br />
the contract was affected by the Force Majeure Event;<br />
iii) the effect which such Force Majeure Event is having on the performance of<br />
contractor’s obligations under the Contract was affected by the Force Majeure<br />
Event;<br />
iv) the measures which the contractor has taken, or proposes to take, to alleviate the<br />
impact of those Force Majeure Events or mitigate the damage; and<br />
v) any other relevant information.