16<br />

42. IDLE TIME CHARGES<br />

<strong>No</strong> IDLE time charge for any of the dredgers/plants/will be paid due to any breakdown/other<br />

hindrance to the dredging.<br />

If dredging is suspended due to force majeure, fire, riots, strikes, civil<br />

commotion/Court’s directive, Shipyard will not be responsible for any consequent<br />

damage or cost involved, including idling charges of the dredger. However suitable<br />

extension for completion of Dredging assignment will be considered on merit of each<br />

case.<br />

During the course of dredging, if the dredger encounters materials like boulders scrap<br />

metals, any other scrap materials in the sea bed, as a result of which either of the<br />

dredger/dredging system is damaged or there is delay in work completion, Cochin<br />

Shipyard shall not be held responsible and any cost incurred including idle time<br />

charges will be to the account of contractor.<br />

Signature, Name and<br />

Address of Contractor,<br />

Date:<br />

Sd/-<br />

General Manager (Tech)