OPERATIONAL CONSTRAINTS - INFRASTRUCTURE<br />
During the summer months of high temperatures, hot weather precautions for track<br />
stability are observed to reduce the risk of incident in accordance with Safety<br />
Management Standard STD/0075/TEC Hot Weather Precautions for Track Stability,<br />
namely :-<br />
Air Temperature 38°C and above - On timber sleepered track, restrict<br />
all trains to 60 km/h (#)<br />
- On concrete sleepered track, restrict<br />
all trains to 120 km/h<br />
Air Temperature 40°C and above - On timber sleepered track, restrict<br />
all trains to 40 km/h (#)<br />
- On concrete sleepered track, restrict<br />
all trains to 60 km/h<br />
(#) Steel sleepered track and timber sleepered track with interspersed steel sleepers<br />
shall be regarded as equivalent to timber sleepered track for track stability.<br />
Speed restrictions may also be put in place after maintenance activities in accordance<br />
with QR Safety Standards.<br />
The extent of restriction will depend upon the type of maintenance activity and risk of<br />
track misalignments.<br />
Force Majeure Events will also see the imposition of speed restrictions, the extent and<br />
severity of the restrictions being dependent on the event.<br />
TRACKSIDE DETECTION EQUIPMENT<br />
Trackside detection equipment is installed on this system to protect below rail<br />
infrastructure and rollingstock from incident.<br />
A summary of locations / equipment type / reporting functions can be found in Appendix<br />
I<br />
WEIGHBRIDGES<br />
There are no weighbridges on this System as described herein.<br />
INFORMATION SYSTEMS<br />
Vizi<strong>Rail</strong> is the key software system designed as a tool for use in integrated scheduling,<br />
possession planning, monitoring and reporting on the QR network.<br />
Functionality includes modules:<br />
Train notices<br />
Actual train running (ATR)<br />
NORTH COAST LINE SYSTEM - SOUTH - INFORMATION PACK<br />
(Nambour - Gladstone and Rocklands to Rockhampton)<br />
ISSUE 2 - JUNE 2007 - 16