May/June 2013 - The ASIA Miner
May/June 2013 - The ASIA Miner
May/June 2013 - The ASIA Miner
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Central Asia<br />
Exploration agreement for East Balkhash project<br />
ORSU Metals Corporation has entered into<br />
an exclusive agreement to jointly explore the<br />
East Balkhash 2 licence area in Kazakhstan.<br />
<strong>The</strong> agreement has been signed with Asem<br />
Tas-N LLC, a privately-owned Kazakh registered<br />
company and owner of the subsoil use<br />
contract for the project.<br />
Orsu is granted the exclusive right for a<br />
period of 175 days, ending in September,<br />
subject to extension by mutual agreement<br />
of the parties, to explore and participate in<br />
the Balkhash project. During this period<br />
Orsu and Asem Tas will continue to jointly<br />
explore the project, including geophysical<br />
works and verification drilling of exploration<br />
targets. Orsu will provide about<br />
US$900,000 in funding for exploration<br />
work, including $130,000 already spent in<br />
<strong>2013</strong> as part of the predecessor agreement.<br />
Asem Tas will apply to transfer the exploration<br />
licence for Balkhash to a new Kazakh<br />
legal entity jointly owned by Orsu and Asem<br />
Tas, which will be a subsidiary of Orsu, with<br />
Orsu holding an effective interest of 55%. A<br />
transfer of the exploration licence to the JV<br />
company will be conditional upon obtaining<br />
a formal waiver of the Kazakh Government’s<br />
pre-emptive right.<br />
On effective transfer of the licence, Orsu<br />
has agreed to pay Asem Tas up to US$1.5<br />
million to compensate it for historical exploration<br />
costs incurred prior to 2012; $20 per<br />
tonne of economically extractable copper<br />
equivalent, up to a maximum of $10 million,<br />
less any amount paid in exploration compensation<br />
on or before completion of a positive<br />
preliminary economic assessment study; and<br />
$20 per additional tonne of economically extractable<br />
copper equivalent, up to a maximum<br />
of $15 million, less any amounts paid<br />
above, on completion of a positive definitive<br />
feasibility study (DFS).<br />
Orsu will finance the works until completion<br />
of the DFS and Orsu will be responsible for<br />
debt financing. Under the terms of the agreement,<br />
Orsu will have the right to buy-out all<br />
or part of the interest of Asem Tas in the JV<br />
company, for cash or shares, at a price determined<br />
by an independent expert.<br />
Meantime, Orsu has appointed Chris<br />
Power as technical director, replacing Raymond<br />
Oates who has resigned from the position.<br />
Chris Power was previously project<br />
manager for the company’s Karchiga project.<br />
Orsu’ primary focus has been the Karchiga<br />
volcanogenic massive sulphide deposit in eastern<br />
Kazakhstan with a total probable reserve<br />
estimate of 10 million tonnes of<br />
sulphide and oxide ore containing 1.666 million<br />
tonnes of copper at an overall average<br />
grade of 1.67%, of which 1.452 million tonnes<br />
is amenable to flotation and 21,400 tonnes<br />
is amenable to heap leaching.<br />
<strong>The</strong> company has received approval for<br />
the Karchiga technical project and expects<br />
to receive the remaining local regulatory approvals<br />
during the current quarter. <strong>The</strong>se<br />
will permit Orsu to commence construction<br />
of mine and processing facilities.<br />
Work continues on Benkala expansion<br />
FRONTIER Mining has resumed operations at<br />
its flagship Benkala Copper Project in northwest<br />
Kazakhstan following the winter shutdown.<br />
Frontier anticipates shipping of cathodes from<br />
Benkala to begin in the first week of <strong>June</strong>.<br />
<strong>The</strong> operations team has been on site over<br />
the past weeks preparing for operational restart<br />
to allow leaching to begin. Agglomerated<br />
ore had been loaded onto pads before December<br />
to facilitate an immediate start-up, without<br />
the need for crushing stockpiled ore, or<br />
depending on activity resuming at the mine.<br />
This year Frontier will continue to work on<br />
the expansion of the Benkala site from an<br />
annual capacity of 7000 tonnes to 10,000<br />
tonnes and will spend an additional US$6<br />
million of Capex on additional leach pads,<br />
improvements to the crushing and agglomeration<br />
process and general site enhancements.<br />
<strong>The</strong> preparations made in 2012<br />
will also allow cathode production to continue<br />
alongside enhancement and expansion<br />
activities at the SX-EW plant.<br />
Frontier’s chairman and CEO Yerlan Aliyev<br />
says, “We are keen to resume operations at<br />
Benkala with all haste. Continued development<br />
of the site offers considerable benefits to<br />
both the company and our shareholders, and<br />
I am in no doubt that is a prudent investment.”<br />
<strong>The</strong> project is about 450km east of Aktobe<br />
(formerly Aktyubinsk) and 100km south of<br />
Zhitigara in northwest Kazakhstan, close to<br />
Trucks lined up for use at the Benkala Copper Project.<br />
Excavation work at Frontier Mining’s Benkala project.<br />
the Russian border. Located within the Urals<br />
copper/gold ore belt, the area presents favourable<br />
geography, the water table is within<br />
25 metres of the surface and the flat landscape<br />
is ideal for heap leach processing.<br />
Current open pit mining targets near surface<br />
oxide mineralization, developed to a<br />
depth of 30 metres. Exploration is under way<br />
at the South Benkala deposit, about 10km<br />
from Benkala, which will benefit from the<br />
newly established infrastructure, extending<br />
the project life span.<br />
Frontier has received credit committee approval<br />
from Sberbank head office in Moscow.<br />
<strong>The</strong> agreement provides KazCopper LLP,<br />
Frontier’s wholly-owned subsidiary, with a<br />
loan and credit facility to the value of US$17.9<br />
million. <strong>The</strong> new facility is for five years and<br />
comprises two components - a US$6 million<br />
increase in the Capital Investment Loan at an<br />
interest rate of 9% and a US$11.9 million increase<br />
in the Working Capital Credit Facility<br />
at an interest rate of 8.5%. Sberbank has<br />
provided Frontier with loan facilities since<br />
2011 and the additional loan brings the total<br />
amount of existing Sberbank facilities to<br />
US$52.9 million.<br />
18 | <strong>ASIA</strong> <strong>Miner</strong> | <strong>May</strong>/<strong>June</strong> <strong>2013</strong>